Construction Act, R.S.O. 1990, c. C.30

Section 17

Limitation on value of lien

Cite as Construction Act, R.S.O. 1990, c. C.30, s. 17 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026

The text

(1) The lien of a person is limited to the amount owing to the person in relation to the improvement and, subject to Part IV (holdbacks), it is further limited to the least amount owed in relation to the improvement by a payer to the contractor or to any subcontractor whose contract or subcontract was in whole or in part performed by the supply of services or materials giving rise to the lien. R.S.O. 1990, c. C.30, s. 17 (1); 2017, c. 24, s. 67. (2) Subject to Part IV, the total value of the liens of all members of a class, as defined in section 79, is limited to the least amount owed in relation to the improvement by a payer to the contractor or to any subcontractor whose contract or subcontract was in whole or in part performed by the supply of services or materials made by the members of the class. R.S.O. 1990, c. C.30, s. 17 (2). (3) Subject to Part IV, in determining the amount of a lien under subsection (1) or (2), there may be taken into account the amount that is, as between a payer and the person the payer is liable to pay, equal to the balance in the payer’s favour of all outstanding debts, claims or damages related to the improvement or, if the contractor or subcontractor, as the case may be, becomes insolvent, all outstanding debts, claims or damages whether or not related to the improvement. R.S.O. 1990, c. C.30, s. 17 (3); 2017, c. 24, s. 14 (1, 2). (4) Despite subsection (1), where land is dedicated to a municipality as a public street or highway and an improvement is made to the land at the written request of, or under an agreement with, the municipality, but not at its expense, the municipality shall nevertheless, on default of payment by the proper payer, be liable to the value of the holdbacks under Part IV that would have been required were the improvement made at the expense of the municipality, and the procedure for making a claim under this subsection shall be the same as for enforcing a claim for lien against a municipality. R.S.O. 1990, c. C.30, s. 17 (4); 2017, c. 24, s. 14 (3); 2017, c. 24, s. 14 (4).
Read the Construction Act on e-Laws ↗