Construction Act, R.S.O. 1990, c. C.30
Section 13.19
Subject to holdback
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 13.19 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) A requirement to pay an amount in accordance with this section is subject to any requirement to retain a holdback in accordance with Part IV. 2017, c. 24, s. 11 (1).
(2) A party who is required under the determination of an adjudicator to pay an amount to another person shall pay the amount no later than 15 days after the determination has been communicated to the parties to the adjudication. 2017, c. 24, s. 11 (1); 2024, c. 20, Sched. 4, s. 23 (1).
(3) Interest begins to accrue on an amount that is not paid when it is due to be paid under this Part, at the prejudgment interest rate determined under subsection 127 (2) of the Courts of Justice Act or, if a contract or subcontract between the parties specifies a different interest rate for the purpose, the greater of the prejudgment interest rate and the interest rate specified in the contract or subcontract. 2017, c. 24, s. 11 (1); 2024, c. 20, Sched. 4, s. 23 (2).
(4) Subsection (3) does not apply in respect of any amount payable under section 6.9. 2017, c. 24, s. 11 (1).
(5) If an amount payable to a contractor or subcontractor under a determination respecting a dispute between the parties to a contract or subcontract is not paid by a party when it is due under this section, the contractor or subcontractor may suspend further work under the contract or subcontract until the party pays the following amounts:
1. The amount required to be paid under the determination.
2. Any interest accrued on that amount under subsection (3).
3. Any reasonable costs incurred by the contractor or subcontractor as a result of the suspension of work. 2017, c. 24, s. 11 (1); 2024, c. 20, Sched. 4, s. 23 (3).
(6) A contractor or subcontractor who suspends work under subsection (5) is entitled to payment, by the party, of any reasonable costs incurred by him or her as a result of the resumption of work following the payment of the amounts referred to in that subsection. 2017, c. 24, s. 11 (1).
Read the Construction Act on e-Laws ↗