Conservation Authorities Act, R.S.O. 1990, c. C.27
Section 28.1
Permits
Cite as Conservation Authorities Act, R.S.O. 1990, c. C.27, s. 28.1 · current to November 11, 2026 · consolidated from April 24, 2026 · read from e-Laws on November 17, 2026
The text
(1) An authority may issue a permit to a person to engage in an activity specified in the permit that would otherwise be prohibited by section 28, if, in the opinion of the authority,
(a) the activity is not likely to affect the control of flooding, erosion, dynamic beaches or unstable soil or bedrock;
(b) the activity is not likely to create conditions or circumstances that, in the event of a natural hazard, might jeopardize the health or safety of persons or result in the damage or destruction of property; and
(c) any other requirements that may be prescribed by the regulations are met. 2017, c. 23, Sched. 4, s. 25; 2022, c. 21, Sched. 2, s. 9 (1).
(2) A person who wishes to engage in an activity that is prohibited under section 28 in an area situated in the jurisdiction of an authority may apply to the authority for a permit under this section. 2017, c. 23, Sched. 4, s. 25.
(3) An application for a permit shall be made in accordance with the regulations and include such information as is required by regulation. 2017, c. 23, Sched. 4, s. 25.
(4) Subject to subsection (5), an authority may issue a permit with or without conditions. 2017, c. 23, Sched. 4, s. 25.
(5) An authority shall not refuse an application for a permit or attach conditions to a permit unless the applicant for the permit has been given an opportunity to be heard by the authority. 2017, c. 23, Sched. 4, s. 25.
(6) In the case of an application for a permit to engage in development related to a renewable energy project as defined in subsection 2 (1) of the Electricity Act, 1998,
(a) the authority shall not refuse the permit unless it is of the opinion that it is necessary to do so to control flooding, erosion, dynamic beaches or unstable soil or bedrock; and
(b) despite subsection (4), the authority shall not attach conditions to the permit unless the conditions relate to controlling flooding, erosion, dynamic beaches or unstable soil or bedrock. 2017, c. 23, Sched. 4, s. 25; 2018, c. 16, s. 3 (2); 2022, c. 21, Sched. 2, s. 9 (2).
(7) If the authority, after holding a hearing, refuses a permit or issues the permit subject to conditions, the authority shall give the applicant written reasons for the decision. 2017, c. 23, Sched. 4, s. 25.
(8) Subject to the regulations, where the authority refuses a permit or imposes any conditions on a permit to which the applicant objects, the applicant may, within 15 days of receiving reasons for the authority’s decision, submit a request to the Minister for the Minister to review the authority’s decision. 2020, c. 36, Sched. 6, s. 16 (2).
(9) Within 30 days after receiving a request under subsection (8), the Minister shall reply to the request and indicate in writing to the applicant and the authority whether or not the Minister intends to conduct a review of the authority’s decision. Failure on the part of the Minister to reply to a request within the 30 day period is deemed to be an indication that the Minister does not intend to review the authority’s decision. 2020, c. 36, Sched. 6, s. 16 (2).
(10) If a reply given under subsection (9) indicates that the Minister intends to conduct a review, the Minister may in the reply require the applicant and the authority to provide the Minister with such information as the Minister considers necessary to conduct the review. 2020, c. 36, Sched. 6, s. 16 (2).
(11) The applicant and the authority shall submit to the Minister such information as was specified in the reply given under subsection (9) within the time period specified in the reply. 2020, c. 36, Sched. 6, s. 16 (2).
(12) The Minister shall publish on the Environmental Registry notice of the Minister’s intention to review a decision made by an authority and shall do so within 30 days of giving a reply to that effect under subsection (9). 2020, c. 36, Sched. 6, s. 16 (2).
(13) The Minister is not required to hold a hearing while conducting a review of an authority’s decision. 2020, c. 36, Sched. 6, s. 16 (2).
(14) Before making a decision with respect to a review, the Minister may confer with any person or body that the Minister considers may have an interest in the review. 2020, c. 36, Sched. 6, s. 16 (2).
(15) After conducting a review of an authority’s decision, the Minister may confirm or vary the authority’s decision or make any decision that the Minister considers appropriate, including issuing the permit subject to conditions. 2020, c. 36, Sched. 6, s. 16 (2).
(16) The Minister shall base any decision under subsection (15) on the criteria set out in clauses (1) (a), (b) and (c). 2020, c. 36, Sched. 6, s. 16 (2).
(17) If, upon conducting a review of an authority’s decision, the Minister decides to refuse to issue a permit or to issue a permit subject to conditions, the Minister shall give the applicant and the authority written reasons for the decision. 2020, c. 36, Sched. 6, s. 16 (2).
(18) If the Minister issues a permit under subsection (15), the Minister shall give a copy of the permit to the authority within five days after the permit is issued. 2020, c. 36, Sched. 6, s. 16 (2).
(19) A decision made by the Minister under subsection (15) is final. 2020, c. 36, Sched. 6, s. 16 (2).
(20) Within 90 days after receiving the reasons for the authority’s decision under subsection (7), the applicant may appeal the authority’s decision to the Ontario Land Tribunal, subject to subsection (21). 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
(21) An applicant who submitted a request under subsection (8) for the Minister to conduct a review of an authority’s decision shall not appeal the decision to the Ontario Land Tribunal under subsection (20) unless,
(a) the Minister’s reply under subsection (9) indicated that the Minister refused to conduct the review; or
(b) 30 days have elapsed following the day the applicant submitted the request for a Minister’s review and the Minister has not made a reply under subsection (9). 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
(22) If an application for a permit is made to the authority and the application complies with subsection (3), and if the authority fails to give the applicant notice of a decision with respect to the application within 90 days after the application is made, the applicant may appeal the application directly to the Ontario Land Tribunal. 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13); 2022, c. 21, Sched. 2, s. 9 (3).
(23) If the Minister indicates in a reply given under subsection (9) that the Minister intends to review an authority’s decision and the Minister fails to make a decision within 90 days of giving the reply, the applicant may, within the next 30 days, appeal the authority’s decision directly to the Ontario Land Tribunal. 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
(24) A notice of an appeal under subsection (20), (22) or (23) shall be sent to the Ontario Land Tribunal and to the authority by registered mail. 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
(25) The Ontario Land Tribunal shall fix a date for a hearing of an appeal under subsection (20), (22) or (23), give notice to all interested parties and give all necessary direction for the hearing. 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
(26) The Ontario Land Tribunal has authority to take evidence, to refuse the permit or to order the authority to issue the permit, with or without conditions. 2020, c. 36, Sched. 6, s. 16 (2); 2021, c. 4, Sched. 6, s. 39 (13).
Read the Conservation Authorities Act on e-Laws ↗