WELLS, R.R.O. 1990, Reg. 903

Section 14.5

Cite as WELLS, R.R.O. 1990, Reg. 903, s. 14.5 · current to November 11, 2026 · consolidated from January 1, 2020 · read from e-Laws on November 16, 2026

The text

(1) If a new well is constructed by any method and the well is constructed with a well pit, (a) the person constructing the well shall ensure that the well pit is constructed with a diameter that, from the bottom of the well pit to the ground surface, is at least 7.6 centimetres greater than the outside diameter of the well pit; and (b) the person constructing the well shall ensure that the annular space outside the well casing is filled, from the bottom of the well pit to the ground surface, with suitable sealant that will provide the appropriate structural strength to support the weight of persons and vehicles that may move over the area after it is filled. O. Reg. 372/07, s. 15. (2) If the sealant referred to in clause (1) (b) contains cement, (a) it shall be allowed to set according to the manufacturer’s specifications or for 12 hours, whichever is longer; and (b) if, after setting in accordance with clause (a), the sealant has settled or subsided, it shall be topped up to the original level. O. Reg. 372/07, s. 15. (3) Subsections (1) and (2) do not apply to a test hole or dewatering well if abandonment of the test hole or dewatering well is scheduled to take place not later than 180 days after completion of the structural stage of the test hole or dewatering well. O. Reg. 372/07, s. 15.
Read the WELLS on e-Laws ↗

Made under Ontario Water Resources Act, R.S.O. 1990, c. O.40.