ADMINISTRATION OF THE PLAN, R.R.O. 1990, Reg. 892
Section 4.6
Cite as ADMINISTRATION OF THE PLAN, R.R.O. 1990, Reg. 892, s. 4.6 · current to November 11, 2026 · consolidated from March 31, 2026 · read from e-Laws on November 16, 2026
The text
(1) Revoked: O. Reg. 274/10, s. 6.
(2) In order to make a claim under subsection 14 (4) of the Act for a home that is not a post June 30, 2012 home, the owner shall complete and submit to the Corporation a major structural defect form during the major structural defect claim period. O. Reg. 9/09, s. 6; O. Reg. 87/12, s. 3.
(3) After receiving a major structural defect form for a home, the Corporation shall, within the time period specified in subsection (4),
(a) conduct an inspection of the home or an assessment of the claim items listed on the form, without doing an inspection of the home; and
(b) issue to the owner a report setting out the Corporation’s assessment of the claim items listed on the form. O. Reg. 483/05, s. 8; O. Reg. 87/12, s. 3 (2).
(4) For the purpose of subsection (3), the time period is,
(a) the 10 days after the Corporation receives the major structural defect form, if the home has a date of possession on or after October 1, 2003 and before September 1, 2005; or
(b) the 30 days after the Corporation receives the major structural defect form, if the home has a date of possession on or after September 1, 2005. O. Reg. 483/05, s. 8; O. Reg. 87/12, s. 3 (2).
(5) An owner who is the owner of a unit in a residential condominium conversion project and who receives money from the pre-existing elements fund shall, before spending any of the money on the pre-existing elements of the unit in accordance with the expected major repair schedule for the project during the initial period,
(a) if so spending the money could be the subject of a claim under subsection 14 (4) of the Act, make a claim on a major structural defect form in respect of the pre-existing elements of the unit and comply with the process specified in this Regulation for making the claim; and
(b) give the vendor in relation to the project and the Corporation the opportunity to inspect the condition of the pre-existing elements of the unit that are the subject of the claim before any work is done on them. O. Reg. 521/17, s. 8; O. Reg. 118/23, s. 1.
(6) An owner who does not comply with subsection (5) shall be deemed to have waived any right to make a warranty claim or to receive compensation from the guarantee fund in respect of the pre-existing elements of the unit. O. Reg. 521/17, s. 8.
Read the ADMINISTRATION OF THE PLAN on e-Laws ↗
Made under Ontario New Home Warranties Plan Act, R.S.O. 1990, c. O.31.