MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854
Section 240
Cite as MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854, s. 240 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026
The text
(1) A hoist operator shall,
(a) at least once during his or her shift, in accordance with subsection (2),
(i) test for the satisfactory working conditions and holding capacity of the hoist brakes, and
(ii) test the holding capacity of any friction clutch;
(b) at least once in twenty-four hours of use of a hoist, test the overwind and underwind protective devices by operating the hoist into them;
(c) make a trial trip of a shaft conveyance,
(i) through the working part of a shaft if hoisting has been stopped for a period exceeding two hours and the hoist operator has reason to believe that an event may have occurred to cause damage or obstruction to the free and normal movement of the conveyances in the shaft, and
(ii) below any part of a shaft that has been under repair, after the repairs have been completed;
(d) remain at the hoist controls when the hoist is in motion under manual control;
(e) except when the hoist is on automatic control due to a temporary absence of the operator from the hoist controls, set the brakes and controls so that at least two separate and distinct actions are required to put the hoist in motion;
(f) not be in voice communication when the hoist is in motion and under his or her manual control, except during an emergency or during maintenance and examination;
(g) not operate the hoist to transport any person unless at least two brakes can be applied to stop the hoist drum;
(h) not lower persons on an unclutched drum;
(i) when heavy loads or irregularly shaped loads are on or under the shaft conveyance, operate the hoist with caution;
(j) complete the hoist movement required by an executive signal after the hoist movement is begun unless there is a signal to stop or an emergency signal; and
(k) upon receiving three signals, remain at the hoist controls unless advised orally by the person in charge of the conveyance that hoist movement will not be required. R.R.O. 1990, Reg. 854, s. 240; O. Reg. 584/91, s. 6; O. Reg. 31/04, s. 15 (1); O. Reg. 34/14, s.15.
(2) The following applies with respect to the tests required by clause (1) (a):
1. The tests shall be conducted in accordance with a procedure established for the hoist.
2. The hoist operator shall conduct the tests immediately before the hoist is used to move a shaft conveyance that is transporting persons.
3. If the tests have been conducted under paragraph 2 during a shift, it is not necessary to conduct them again during the same shift. O. Reg. 31/04, s. 15 (2).
Read the MINES AND MINING PLANTS on e-Laws ↗
Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.