MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854

Section 225

Cite as MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854, s. 225 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026

The text

(1) Before a sheave is used, a certificate for the sheave shall be obtained from the manufacturer of the sheave or an engineer competent in sheave design certifying as to, (a) the maximum rated load; (b) the diameter of rope for which it was designed; (c) the breaking strength of the rope for which it was designed; and (d) the maximum amount of groove wear that shall be permitted. R.R.O. 1990, Reg. 854, s. 225 (1); O. Reg. 373/22, s. 15 (1). (2) No sheave shall be, (a) loaded above the maximum rated load; or (b) used other than in compliance with the certificate. R.R.O. 1990, Reg. 854, s. 225 (2). (3) The ratio of the diameter of the sheave to the diameter of the rope shall be as prescribed in section 216. R.R.O. 1990, Reg. 854, s. 225 (3). (4) A sheave shall, (a) be made of materials which will safely withstand the ambient temperatures; (b) be fitted with a groove to fit the rope being used; and (c) bear a serial number and the date of its manufacture. R.R.O. 1990, Reg. 854, s. 225 (4). (5) The shaft of a sheave shall be examined for flaws using the appropriate non-destructive test or tests, (a) before being put into service in a particular location; (b) after installation; and (c) at a regular frequency at least equal to that recommended by a person certified in accordance with section 1.1 or by an engineer. O. Reg. 187/19, s. 14; O. Reg. 373/22, s. 15 (2).
Read the MINES AND MINING PLANTS on e-Laws ↗

Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.