MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854
Section 213
Cite as MINES AND MINING PLANTS, R.R.O. 1990, Reg. 854, s. 213 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026
The text
A certificate for each hoist shall be obtained from the manufacturer of the hoist or an engineer competent in the design of mine hoisting plants certifying,
(a) the maximum rope pull;
(b) the maximum suspended load; and
(c) the maximum unbalanced load in the case of a friction hoist,
and no hoist shall be loaded above the maximums as certified. R.R.O. 1990, Reg. 854, s. 213; O. Reg. 373/22, s. 13.