GENERAL, R.R.O. 1990, Reg. 18
Section 11
Cite as GENERAL, R.R.O. 1990, Reg. 18, s. 11 · current to November 11, 2026 · consolidated from July 1, 2021 · read from e-Laws on November 16, 2026
The text
(1) Except in the case of machines that, in the opinion of the Director, are used solely for demonstration purposes, every machine shall,
(a) be capable of excavating a trench or laying tile to a grade that does not deviate from the grade established by the drainage work plan by more than,
(i) 15 per cent of the internal diameter of the tile where the diameter is eight inches or less, or
(ii) 10 per cent of the internal diameter of the tile, where the diameter exceeds eight inches; and
(b) for the purpose of excavating trenches, be equipped with a wheel, chain or other device capable of excavating a trench that exceeds the diameter of the tile to be installed by at least six inches. R.R.O. 1990, Reg. 18, s. 11 (1).
(2) For the purposes of subsection (1),
(a) the grade deviation allowed by clause (a) of that subsection is subject to the conditions that such deviations,
(i) occur on a gradual basis over a distance of not less than thirty feet, and
(ii) do not occur consecutively above and below the established grade within a distance of 100 feet; and
(b) the trench width mentioned in clause (b) of that subsection shall be measured at a level above the trench bottom equal to the diameter of the tile. R.R.O. 1990, Reg. 18, s. 11 (2).
Read the GENERAL on e-Laws ↗
Made under Agricultural Tile Drainage Installation Act, R.S.O. 1990, c. A.14.