English and Wabigoon River Systems Mercury Contamination Settlement Agreement Act, 1986, S.O. 1986, c. 23
Section 21
Decision final
Cite as English and Wabigoon River Systems Mercury Contamination Settlement Agreement Act, 1986, S.O. 1986, c. 23, s. 21 · current to November 11, 2026 · consolidated from July 28, 1986 · read from e-Laws on November 17, 2026
The text
(1) The Board has exclusive jurisdiction to exercise the powers conferred upon it by this Act and to determine all questions of fact and law that arise in any matter before it and, subject to sections 20 and 23, every decision of the Board is final and binding and is not subject to review and, subject to this Act, shall be given effect by the administrator.
(2) The Statutory Powers Procedure Act does not apply to the Board in its exercise of a statutory power of decision under this Act.
Read the English and Wabigoon River Systems Mercury Contamination Settlement Agreement Act, 1986 on e-Laws ↗