CORE EDUCATION FUNDING - LEGISLATIVE GRANTS FOR THE 2026-2027 SCHOOL BOARD FISCAL YEAR, O. Reg. 298/26
Section 150
Base school renewal component
Cite as CORE EDUCATION FUNDING - LEGISLATIVE GRANTS FOR THE 2026-2027 SCHOOL BOARD FISCAL YEAR, O. Reg. 298/26, s. 150 · current to November 11, 2026 · consolidated from August 31, 2026 · read from e-Laws on November 16, 2026
The text
The base school renewal component is determined as follows:
1. Take the geographic adjustment factor specified for the board in Table 41.
2. Take the percentage of the total elementary school area that relates to buildings that are less than 20 years old, as specified for the board in Column 2 of Table 42.
3. Apply the percentage referred to in paragraph 2 to the benchmark renewal cost per metre squared of $7.89.
4. Take the percentage of the total elementary school area that relates to buildings that are 20 years old or older, as specified for the board in Column 3 of Table 42.
5. Apply the percentage referred to in paragraph 4 to the benchmark renewal cost per metre squared of $11.83.
6. Total the amounts determined under paragraphs 3 and 5 to obtain a weighted average benchmark elementary school renewal cost per metre squared.
7. Determine the adjusted elementary school area requirement for the board in metres squared by applying, to the amount determined under paragraph 2 of section 141, the supplementary elementary school area factor specified for the board in Column 2 of Table 38.
8. Multiply the amount determined under paragraph 6 by the amount determined under paragraph 7.
9. Take the percentage of the total secondary school area that relates to buildings that are less than 20 years old, as specified for the board in Column 4 of Table 42.
10. Apply the percentage referred to in paragraph 9 to the benchmark renewal cost per metre squared of $7.89.
11. Take the percentage of the total secondary school area that relates to buildings that are 20 years old or older, as specified for the board in Column 5 of Table 42.
12. Apply the percentage referred to in paragraph 11 to the benchmark renewal cost per metre squared of $11.83.
13. Total the amounts determined under paragraphs 10 and 12 to obtain a weighted average benchmark secondary school renewal cost per metre squared.
14. Determine the adjusted secondary school area requirement for the board in metres squared by applying, to the amount determined under paragraph 12 of section 141, the supplementary secondary school and continuing education area factor specified for the board in Column 3 of Table 38.
15. Multiply the amount determined under paragraph 13 by the amount determined under paragraph 14.
16. Multiply the amount determined under paragraph 13 by the adjusted continuing education and other programs area requirement for the board determined under paragraph 10 of section 141.
17. Total the amounts determined under paragraphs 8, 15 and 16.
18. Multiply the sum determined under paragraph 17 by the geographic adjustment factor taken under paragraph 1.