GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER, O. Reg. 12/26

Section 66

Daily record and tour sheet requirements

Cite as GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER, O. Reg. 12/26, s. 66 · current to November 11, 2026 · consolidated from February 1, 2026 · read from e-Laws on November 16, 2026

The text

(1) A permit holder shall maintain daily records of drilling, completion, workover and decommissioning operations on a well from the start of the operation to rig release that include, at a minimum, the documents and information set out in subsection (5). (2) A permit holder shall ensure that a tour sheet is prepared for each shift of a drilling crew or of other related operations from the start of the operation to rig release. (3) All tour sheets must be submitted to the Ministry by the permit holder within 30 days after rig release. (4) Any information set out in a daily record that is not contained in a tour sheet or in the report under section 64 must be provided to the Ministry by the permit holder within 60 days after rig release. (5) Daily records under subsection (1) must include the following: 1. The following identification information for the well: i. The unique well identification number. ii. Well location. iii. Rig number. iv. Kelly bushing elevation. v. Surveyed ground elevation. 2. A record of operations in chronological order, including start and end times for each tour. 3. The name of each contractor working on the well and any ancillary works during each tour or shift and the activities each contractor was responsible for performing. 4. The following details regarding drilling, including drilling when deepening and sidetracking: i. Spud date. ii. Depth at start and end of each tour. iii. Deviation surveys and whipstock depths. iv. Total depth of the well at termination of drilling. v. Diameter of the hole. 5. The following details regarding casing and liners: i. Size, type, grade and weight. ii. Specifications, name of manufacturer and casing tally. iii. Setting depth. iv. Installation history, including details of any issues encountered during casing or liner installation. v. Float equipment and casing attachments used. 6. Completion information including packers, perforations, acidizing, squeeze jobs and fracture stages. 7. Wellhead pressures if observed at the start and end of each tour. 8. Depth at the start and end of each tour. 9. Geological observations, including gas, oil or water shows or flows. 10. Fishing operations. 11. Total depth of the well. 12. Bottomhole assembly specification. 13. Rig release date. 14. Details of any pressure tests used to verify the seal and structural integrity of temporary or permanent barriers installed in a wellbore. 15. Any operational issues or changes to the drilling, completion, workover or decommissioning programs. 16. The following cementing details: i. Cement blends used, including cement type and additives. ii. Source of mix water. iii. Type and volume of any preflush. iv. Volumes of cement pumped. v. Cement slurry density. vi. Actual and final displacement volumes and pressure. vii. Observation of cement returns, including an estimation of the volume of cement returns. viii. Results of every pressure test after cementing. ix. Cement tops and how they were identified, such as by logging. 17. Information about circulation losses outlining the depth and interval of loss, mud density and volume lost, and the materials used for remediation. 18. Kick control information outlining the depth of the kick, shut-in and circulating pressures and influx volume and control procedures. 19. The following information about geological formation testing: i. Drill stem tests conducted, including test number, interval, valve times, flow rates, recovered volumes and pressure data. ii. Wireline tests conducted, including test number, depth, duration and recovery pressure data. iii. Flow tests conducted, including flow rates, depths, recoveries and fluid analysis. iv. Fluid geochemical analyses. v. Swab tests conducted, including depths, recoveries and fluid levels. vi. Core samples collected, including interval, size, lithology and recovery. 20. Formation evaluation logs and any cased-hole cement bond logs, including details of all logs and their depth intervals, together with associated interpretive and engineering reports. 21. Decommissioning information, including plugging and plug details and surface abandonment method. 22. The following safety and environmental information: i. Blowout preventer and choke manifold pressure tests conducted. ii. Air shut-off tests conducted. iii. Blowout preventer drills conducted. iv. Spill notifications and actions taken.
Read the GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER on e-Laws ↗

Made under Geologic Carbon Storage Act, 2025, S.O. 2025, c. 17, Sched. 2.