GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER, O. Reg. 12/26

Section 11

Application for permit, plans

Cite as GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER, O. Reg. 12/26, s. 11 · current to November 11, 2026 · consolidated from February 1, 2026 · read from e-Laws on November 16, 2026

The text

(1) An application for a permit shall also include plans that address how the activities associated with the carbon storage site will be carried out throughout the lifecycle of the project. (2) The plans referred to in subsection (1) must include, (a) plans for the design, construction, operation, maintenance, decommissioning, remediation, restoration and closure of the carbon storage site, which must include the plans and documents referred to in subsection (5); (b) plans for managing risk; (c) plans for monitoring, measuring and verifying project performance and risks; and (d) plans for managing and responding to emergencies. (3) An application for a permit shall also include any additional supporting information in respect of the plans referred to in subsection (2) that is required to demonstrate that, (a) the requirements and recommendations set out in CSA Z741 for risk management have been and will continue to be complied with; and (b) subject to any departures under subsection 38 (4), (i) the requirements and recommendations set out in CSA Z741 for well infrastructure and closure will be complied with, and (ii) monitoring, measurement and verification will be carried out in accordance with the requirements and recommendations set out in CSA Z741and CSA TS-226. (4) If a departure under subsection 38 (4) is proposed in a plan that is submitted as a part of an application for a permit, the report referenced in paragraph 2 of subsection 38 (4) must be submitted with the proposed plan. (5) The plans and documents mentioned in clause (2) (a) are, (a) plans for the location of all wells that indicate, (i) the surface and bottomhole location of each well, (ii) the ground elevation of the surface location of each well above mean sea level, (iii) all dwellings and agricultural, commercial or industrial buildings, schools, churches, places of public assembly, high voltage power lines, road allowances, transmission pipelines or other occupied utility rights of way as well as rivers, streams and shorelines that are located within 100 metres of the surface location of each well and the proximity of each of them to the well, and (iv) for each horizontal or deviated well, (A) the proposed well bore trace, bottomhole location and location at which the well bore enters the target formation, and (B) a cross-sectional plan showing the target geological formation as anticipated by the geological prognosis, the direction of the deviated or horizontal well bore and the kick-off point of the well bore; (b) a schedule outlining the anticipated timeline for completing the project; (c) a schedule outlining the anticipated timeline for and the estimated costs, including an itemized list of each of those costs, of, (i) decommissioning all wells, storage repositories and ancillary works that form part of the carbon storage site, (ii) carrying out all necessary site remediation and restoration activities, and (iii) any maintenance, monitoring, measurement or verification activities required both during the performance of the activities referred to in subclauses (i) and (ii) as well as after their completion and before the end of the applicable closure period under section 77; and (d) if the applicant proposes to establish the security required under this Regulation in phases, a plan setting out, (i) the proposed phases for which security would be established, which must be aligned with the proposed plans for construction, (ii) clear milestones that identify the beginning and end of each phase, (iii) an indication of the wells, storage repositories and ancillary works that would form part of the carbon storage site during each phase and the costs referred to in clause (c) associated with each of them during each phase, and (iv) the security amount for each phase, which must equal the total of the costs referred to in clause (c) associated with the wells, storage repositories and ancillary works that would form part of the carbon storage site during the phase or has formed part of the carbon storage site during a previous phase. (6) The measurements used to prepare the well location plans referred to in clause (5) (a) must, (a) be presented in the International System of Units; (b) use Universal Transverse Mercator coordinates based on the North American Datum 83, measured and reported to the nearest tenth of a metre; (c) be accurate to the nearest tenth of a metre for linear measurements; (d) be accurate to the nearest degree or minute for angular measurements where applicable, such as when describing wellbore trajectory; and (e) be surveyed from a vertical benchmark referenced to Geodetic Surveys of Canada based on North American Datum 83 for ground elevation measurements and be accurate to the nearest tenth of a metre. (7) For the purposes of clause (5) (d), the costs associated with any wells or ancillary works that would form part of the carbon storage site and that already exist when the application is submitted must be included as part of the first proposed phase under that clause, even if the well or ancillary work would only form part of the carbon storage site during a subsequent phase. (8) Any plans for managing risk and any plans for monitoring, measuring and verifying project performance and risks submitted as part of an application for a storage permit must be reviewed by an expert. However, this review may occur either before or after the application is submitted to the Ministry under section 14. (9) Plans for site remediation and restoration that aim to return the site to its natural or original condition must include a detailed description of the site’s existing baseline condition before the performance of any research and evaluation activities or carbon storage activities. (10) Plans that propose the use of materials for which the CSA Z741 does not reference an applicable standard or specification for the intended use, must be accompanied by an engineering assessment that, (a) includes an evaluation of technical data or any applicable material standard or specification not referenced in CSA Z741 for that intended use; and (b) demonstrates that the materials are safe for the conditions to which they will be subjected.
Read the GENERAL MATTERS UNDER THE AUTHORITY OF THE MINISTER on e-Laws ↗

Made under Geologic Carbon Storage Act, 2025, S.O. 2025, c. 17, Sched. 2.