GENERAL MATTERS UNDER THE AUTHORITY OF THE LIEUTENANT GOVERNOR IN COUNCIL, O. Reg. 311/25
Section 23
Transition, well licence and injection permit applications
Cite as GENERAL MATTERS UNDER THE AUTHORITY OF THE LIEUTENANT GOVERNOR IN COUNCIL, O. Reg. 311/25, s. 23 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
(1) Subject to subsection (5), an application for a well licence, as well as an application for an injection permit, if applicable, are deemed to be an application for a research and evaluation permit that meets any requirements established by the regulations for submission of the application to the Minister if,
(a) the application or applications relate to a special project that was designated as such under section 11.1 of the Oil, Gas and Salt Resources Act before the transition period; and
(b) before the transition period,
(i) the application or applications were submitted to the Ministry for preliminary assessment under section 11 of the Special Projects Regulation and, in the Minister’s opinion, the application or applications met all of the requirements of section 10 of the Special Projects Regulation, and
(ii) the applicant has notified the Ministry, no later than July 1, 2026, that the applicant intends to relinquish the applicant’s special project designation and instead seek to perform research and evaluation activities in accordance with the Act.
(2) For greater certainty, the report that, under clause 10 (4) (d) of the Special Projects Regulation, accompanied the application for a well licence and, if applicable, the report that accompanied the application for an injection permit under that clause are deemed to constitute any similar report required to be included by the regulations in an application for a research and evaluation permit.
(3) If an application or applications are deemed to be an application for a research and evaluation permit under subsection (1), the applicant is exempt from the requirement to pay any application fee for the research and evaluation permit.
(4) Within 15 days after having received the notification from the applicant referred to in subclause (1) (b) (ii), the Ministry shall provide the applicant with a notice identifying any Indigenous communities or organisations or ministries or agencies of the provincial or federal government or of neighbouring provinces or states identified by Ministry personnel that must be notified in accordance with the requirements prescribed for the purposes of clause 12 (1) (b) of the Act.
(5) If the applicant fails to give notice of the application for a research and evaluation permit in accordance with the requirements prescribed for the purposes of clause 12 (1) (b) of the Act within six months after receiving the notice referred to in subsection (4), the application for a well licence and any application for an injection permit are no longer deemed to be an application for a research and evaluation permit and the applicant is no longer exempt from the requirement referred to in subsection (3).
Read the GENERAL MATTERS UNDER THE AUTHORITY OF THE LIEUTENANT GOVERNOR IN COUNCIL on e-Laws ↗
Made under Geologic Carbon Storage Act, 2025, S.O. 2025, c. 17, Sched. 2.