New stations
Cite as GENERAL, O. Reg. 207/25, s. 4 · current to November 11, 2026 · consolidated from September 2, 2025 · read from e-Laws on November 16, 2026
The text
(1) For the purposes of subsection 3 (3) of the Act, construction of a GO Transit station begins on the day on which machinery or equipment is first operated in connection with the construction of a building or structure that is part of the station.
(2) For greater certainty, any activity performed to prepare a site for the construction of a building or structure mentioned in subsection (1) does not begin the construction of a GO Transit station.