REGISTRATIONS UNDER PART II.2 OF THE ACT — STORM WATER MANAGEMENT WORKS, O. Reg. 137/25
Section 26
Continuation of applications for environmental compliance approval
Cite as REGISTRATIONS UNDER PART II.2 OF THE ACT — STORM WATER MANAGEMENT WORKS, O. Reg. 137/25, s. 26 · current to November 11, 2026 · consolidated from September 1, 2026 · read from e-Laws on November 16, 2026
The text
(1) If an application for approval to engage in an activity mentioned in subsection 53 (1) of the Ontario Water Resources Act that is prescribed by this Regulation for the purposes of subsection 20.21(1) of the Act is submitted to the Director on or before the day the provision of a regulation that results in the activity being prescribed comes into force and the Director did not make a decision with respect to the application before that day, the application is exempt from subsections 20.2 (3) and 20.3 (2) of the Act. O. Reg. 234/26, s. 18.
(2) A person who is engaging in an activity in respect of which an application for approval described in subsection (1) has been made is exempt from subsection 20.21 (1) of the Act until the earliest of the following days:
1. The day the person withdraws the application.
2. The day the Director refuses to issue an environmental compliance approval in respect of the activity.
3. If the Director issues an environmental compliance approval in respect of the activity, the day the approval ceases to apply in respect of the activity as determined under section 20.17 of the Act. O. Reg. 137/25, s. 26 (2).
Read the REGISTRATIONS UNDER PART II.2 OF THE ACT — STORM WATER MANAGEMENT WORKS on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.