AIR POLLUTION — DISCHARGE OF BENZENE FROM INEOS STYROLUTION, O. Reg. 206/24

Section 10

Benzene monitoring

Cite as AIR POLLUTION — DISCHARGE OF BENZENE FROM INEOS STYROLUTION, O. Reg. 206/24, s. 10 · current to November 11, 2026 · consolidated from August 29, 2024 · read from e-Laws on November 16, 2026

The text

(1) The owner and operator of the INEOS Styrolution facility shall ensure that, (a) the fenceline monitoring system begins operating no later than the date set out in the accepted monitoring plan for the system; (b) the open path monitoring system begins operating no later than the date set out in the accepted monitoring plan for the system; (c) the leak detection monitoring system begins operating no later than the date set out in the accepted monitoring plan for the system; and (d) the back-up measurement methods are available to be used no later than the date set out in the accepted monitoring plan for the methods. (2) No later than the date set out in Column 1 of the Table to this subsection, the owner and operator of the INEOS Styrolution facility shall comply with the requirements set out in Column 2 opposite the date. Item | Column 1 Compliance Date | Column 2 Requirements set out in the accepted monitoring plan 1. | The date set out in the accepted monitoring plan as the date that the fenceline monitoring system will begin operating. | 1. The requirements set out in the accepted monitoring plan as described in paragraphs 1, 5, 6, 8 and 14 of subsection 5 (1). 2. The requirements set out in the accepted monitoring plan as described in paragraphs 7 and 9 to 13 of subsection 5 (1) as the requirements relate to the fenceline monitoring system. 2. | The date set out in the accepted monitoring plan as the date that the open path monitoring system will begin operating. | 1. The requirements set out in the accepted monitoring plan as described in paragraphs 2 and 14 of subsection 5 (1). 2. The requirements set out in the accepted monitoring plan as described in paragraphs 7 and 9 to 13 of subsection 5 (1) as the requirements relate to the open path monitoring system. 3. | The date set out in the accepted monitoring plan as the date that the leak detection monitoring system will begin operating. | 1. The requirement set out in the accepted monitoring plan as described in paragraph 3, 4 and 14 of subsection 5 (1). 2. The requirements set out in the accepted monitoring plan as described in paragraphs 7 and 11 to 13 of subsection 5 (1) as the requirements relate to the leak detection monitoring system. (3) No later than the full implementation date set out in the accepted monitoring plan, the owner and operator of the INEOS Styrolution facility shall comply with the requirements set out in the plan. (4) The owner and operator of the INEOS Styrolution facility shall ensure that, of all the measurements that are required to be taken by a monitor in the fenceline monitoring system or a detector in the open path monitoring system in any 90-day period, at least 90 per cent of the measurements that the monitor or detector is required to take are valid. (5) For the purposes of subsection (4), a required measurement that is not taken by a monitor or detector is considered an invalid measurement. (6) For greater certainty, the owner and operator of the INEOS Styrolution facility shall also comply with any other requirement to measure the concentration of benzene in the air, including any requirement set out in, (a) a notice given under subsection 9 (1); (b) the Petrochemical Industry Standard in accordance with subsection 42 (5) of Ontario Regulation 419/05 (Air Pollution — Local Air Quality) made under the Act; (c) an order under the Act issued in respect of the INEOS Styrolution facility; and (d) an environmental compliance approval issued in respect of the INEOS Styrolution facility. (7) During any period when a monitor that is required to be operated under a requirement described in clause (6) (a), (c) or (d) fails to accurately measure the concentration of benzene in the air for 24 hours or more, the owner and operator of the INEOS Styrolution facility shall use a back-up measurement method during the period to accurately measure the concentration of benzene in the air at least every 24 hours at the location of the monitor. (8) The owner and operator of the INEOS Styrolution facility shall ensure that measurements taken under subsection (7) are validated and that the back-up measurement methods are calibrated and maintained. (9) If any requirement to measure the concentration of benzene in the air under this Regulation or a requirement described in subsection (6) involves laboratory analysis, the analysis shall be performed by a laboratory that has been accredited in accordance with the International Standard ISO/IEC 17025 – General Requirement for the Competence of Testing and Calibration Laboratories, dated May 5, 2005, as amended from time to time.
Read the AIR POLLUTION — DISCHARGE OF BENZENE FROM INEOS STYROLUTION on e-Laws ↗

Made under Environmental Protection Act, R.S.O. 1990, c. E.19.