EXEMPTIONS FROM THE ACT AND FROM PART II.1 OF THE ACT, O. Reg. 51/24
Section 7
Trafalgar to Oakville transmission line
Cite as EXEMPTIONS FROM THE ACT AND FROM PART II.1 OF THE ACT, O. Reg. 51/24, s. 7 · current to November 11, 2026 · consolidated from November 3, 2026 · read from e-Laws on November 16, 2026
The text
(1) The establishing of a transmission line that extends from the Trafalgar Transmission Station located at 1600 E Lower Base Line, Milton, Ontario to the Oakville Transmission Station located at 1559 Maplegrove Drive, Oakville, Ontario is exempt from the Act if the construction of the transmission line is an undertaking to which exemption order OHK-11 applied.
(2) In this section,
“exemption order OHK-11” means the order made under section 30 of the Act, as it read on October 14, 1976, identified as order OHK-11, dated October 14, 1976 and approved by Order in Council 2887/76.
Read the EXEMPTIONS FROM THE ACT AND FROM PART II.1 OF THE ACT on e-Laws ↗