PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24

Section 9

Electricity projects, environmental screening

Cite as PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24, s. 9 · current to November 11, 2026 · consolidated from November 3, 2026 · read from e-Laws on November 16, 2026

The text

Subject to sections 11 and 12, establishing any of the following things is designated as a project to which Part II.3 of the Act applies: 1. A generation facility that has a name plate capacity of greater than or equal to one megawatt but less than five megawatts and that uses oil as its primary power source. 2. A generation facility that has a name plate capacity of greater than or equal to two megawatts and that uses wind energy as its primary power source. 3. A generation facility that has a name plate capacity of greater than or equal to five megawatts and that uses biomass or natural gas as its primary power source. 4. A generation facility that has a name plate capacity of greater than or equal to 10 megawatts and that uses waste biomass as its primary power source. 5. A generation facility that has a name plate capacity of greater than or equal to 25 megawatts and that uses biogas as its primary power source. 6. A generation facility that has a name plate capacity of greater than or equal to 25 megawatts, uses landfill gas as its primary power source and is located at a waste disposal site the establishment of which does not or did not require approval under the Act. 7. A generation facility that has a name plate capacity of less than 200 megawatts and that uses water power as its primary power source. 8. A transmission line that, i. is not associated with a generation facility described in this section, ii. is greater than two kilometres in length, and iii. has a nominal operating voltage of greater than or equal to 115 kilovolts. 9. A transmission line that has a nominal operating voltage of greater than or equal to 115 kilovolts and is associated with a generation facility described in this section. 10. A transmission station that has a nominal operating voltage of greater than or equal to 115 kilovolts.
Read the PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS on e-Laws ↗

Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.