PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24
Section 9
Electricity projects, environmental screening
Cite as PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS, O. Reg. 50/24, s. 9 · current to November 11, 2026 · consolidated from November 3, 2026 · read from e-Laws on November 16, 2026
The text
Subject to sections 11 and 12, establishing any of the following things is designated as a project to which Part II.3 of the Act applies:
1. A generation facility that has a name plate capacity of greater than or equal to one megawatt but less than five megawatts and that uses oil as its primary power source.
2. A generation facility that has a name plate capacity of greater than or equal to two megawatts and that uses wind energy as its primary power source.
3. A generation facility that has a name plate capacity of greater than or equal to five megawatts and that uses biomass or natural gas as its primary power source.
4. A generation facility that has a name plate capacity of greater than or equal to 10 megawatts and that uses waste biomass as its primary power source.
5. A generation facility that has a name plate capacity of greater than or equal to 25 megawatts and that uses biogas as its primary power source.
6. A generation facility that has a name plate capacity of greater than or equal to 25 megawatts, uses landfill gas as its primary power source and is located at a waste disposal site the establishment of which does not or did not require approval under the Act.
7. A generation facility that has a name plate capacity of less than 200 megawatts and that uses water power as its primary power source.
8. A transmission line that,
i. is not associated with a generation facility described in this section,
ii. is greater than two kilometres in length, and
iii. has a nominal operating voltage of greater than or equal to 115 kilovolts.
9. A transmission line that has a nominal operating voltage of greater than or equal to 115 kilovolts and is associated with a generation facility described in this section.
10. A transmission station that has a nominal operating voltage of greater than or equal to 115 kilovolts.
Read the PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS on e-Laws ↗