(1) Establishing one or more works is designated as a project to which Part II.3 of the Act applies if the works, taken together,
(a) alter at least one kilometre of shoreline in the Great Lakes-St. Lawrence River system; and
(b) require at least four hectares of lakebed or riverbed in the Great Lakes-St. Lawrence River system to be filled.
(2) For greater certainty, if a single works or any combination of works satisfies clauses (1) (a) and (b), the works or combination of works is a Part II.3 project.
(3) The length of shoreline in clause (1) (a) and the area of lakebed or riverbed in clause (1) (b) do not include the length of any shoreline or area of any lakebed or riverbed, respectively, of a tributary of the Great Lakes-St. Lawrence River system, other than the mouth of the tributary.
(4) In this section,
“Great Lakes-St. Lawrence River system” means the major water system consisting of,
(a) Lake Ontario, Lake Erie, Lake Huron, Lake Superior and Lake St. Clair,
(b) the St. Marys, St. Clair, Detroit, Niagara and St. Lawrence Rivers, and
(c) the mouth of any tributary to a water body mentioned in clauses (a) and (b); (“réseau hydrographique des Grands Lacs et du Saint-Laurent”)
“works” means any thing that may be established on or near a waterfront, including a beach, berm, breakwall, channel, groyne, island, marina, pier or riprap. (“ouvrage”)
Part V Shoreline and in-water works Projects
Interpretation
26. In this Part,
“shoreline” means the interface between land and water; (“rivage”)
“works” means any thing that may be established on or near a shoreline, including a beach, berm, breakwall, channel, groyne, island, marina, pier or riprap. (“ouvrage”) O. Reg. 257/26, s. 4.
Part II.3 shoreline and in-water works projects
27. (1) Establishing one or more works is designated as a project to which Part II.3 of the Act applies if the works, taken together,
(a) alter at least one kilometre of shoreline in the Great Lakes-St. Lawrence River system; and
(b) require at least four hectares of lakebed or riverbed in the Great Lakes-St. Lawrence River system to be filled. O. Reg. 257/26, s. 4.
(2) For greater certainty, if a single works or any combination of works satisfies the criteria referred to in clauses (1) (a) and (b), the works or combination of works is a Part II.3 project. O. Reg. 257/26, s. 4.
(3) The length of shoreline referred to in clause (1) (a) and the area of lakebed or riverbed referred to in clause (1) (b) do not include the length of any shoreline or area of any lakebed or riverbed, respectively, of a tributary of the Great Lakes-St. Lawrence River system, other than the mouth of the tributary. O. Reg. 257/26, s. 4.
(4) In this section,
“Great Lakes-St. Lawrence River system” means the major water system consisting of,
(a) Lake Ontario, Lake Erie, Lake Huron, Lake Superior and Lake St. Clair,
(b) the St. Marys, St. Clair, Detroit, Niagara and St. Lawrence Rivers, and
(c) the mouth of any tributary to a water body mentioned in clauses (a) and (b). O. Reg. 257/26, s. 4.
Part II.4 shoreline and in-water works projects
28. (1) Establishing any of the following things is designated as projects to which Part II.4 of the Act applies, if section 27 does not apply in respect of the establishing and the establishing is carried out by a municipality:
1. A conveyance system that conveys water from one watercourse to another.
2. A dam, other than a coffer dam or a rock vortex weir.
3. An erosion works in or along the shoreline of a waterbody that is not a watercourse. O. Reg. 257/26, s. 4.
(2) Subsection (1) does not apply to,
(a) an activity that is part of an undertaking referred to in section 15 of the Act;
(b) extending, expanding or changing the capacity of a conveyance system, erosion works or dam listed in subsection (1); or
(c) reconstructing or replacing a conveyance system, erosion works or dam listed in subsection (1), in its current location. O. Reg. 257/26, s. 4.
(3) For greater certainty, if a thing listed in subsection (1) is replaced and the replacement is located somewhere different from the original, replacing the thing is deemed to be establishing the thing, even if the replacement is the same as the original. O. Reg. 257/26, s. 4.
(4) In this section,
“conveyance system” includes structures such as channels, drains, swales, pipes and ditches; (“système d’acheminement”)
“erosion works” means a works that rehabilitates, protects or manages a shoreline by preventing erosion or controlling sediment exchange between land and water, such as a breakwall that protects a shoreline from eroding. (“ouvrage de lutte contre l’érosion”) O. Reg. 257/26, s. 4.
Part II.4 shoreline and in-water works projects, archaeological focus
29. (1) The following activities are designated as projects to which Part II.4 of the Act applies, if neither section 27 nor 28 applies in respect of the activity and the activity is carried out by a municipality:
1. An activity carried out in or along a watercourse for the purposes of flood control or erosion control, including,
i. bank or slope regrading,
ii. relocating, realigning or channelizing the watercourse,
iii. installing rock riffles, and
iv. constructing revetments, rock vortex weirs or berms.
2. Making a change to a water crossing for the purposes of flood control.
3. Constructing a spillway for erosion or sedimentation control at an outfall of a pipe, sewer, drainage channel or other structure or thing that discharges into a watercourse or water body.
4. Constructing a fish ladder in a natural watercourse.
5. Making a change to a dam that would result in a change to the dam’s footprint.
6. Enclosing a watercourse in a storm sewer. O. Reg. 257/26, s. 4.
(2) Subsection (1) does not apply in respect of an activity that is part of an undertaking referred to in section 15 of the Act. O. Reg. 257/26, s. 4.
Read the PART II.3 PROJECTS - DESIGNATIONS AND EXEMPTIONS on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.