REHABILITATION OF LANDS, O. Reg. 35/24

Section 28

Transition, no filed closure plan

Cite as REHABILITATION OF LANDS, O. Reg. 35/24, s. 28 · current to November 11, 2026 · consolidated from April 1, 2024 · read from e-Laws on November 16, 2026

The text

(1) This section applies if there is no filed closure plan with respect to a project on the transition date. (2) If the circumstances specified in subsection (3) apply, the proponent is not required to comply with the requirements of subparagraph 2 ii of Schedule 2 to provide qualified person certificates with respect to the submission of a closure plan, other than certificates for the purposes of subsection 4 (3). (3) Subsection (2) applies if, (a) the Notice of Project Status for the closure plan was submitted before the transition date or within three months after it; and (b) the closure plan is submitted no later than the second anniversary of the transition date.
Read the REHABILITATION OF LANDS on e-Laws ↗

Made under Mining Act, R.S.O. 1990, c. M.14.