REHABILITATION OF LANDS, O. Reg. 35/24

Section 20

Effect of temporary suspension

Cite as REHABILITATION OF LANDS, O. Reg. 35/24, s. 20 · current to November 11, 2026 · consolidated from April 1, 2024 · read from e-Laws on November 16, 2026

The text

A proponent that complies with a corporate financial test and that places a project into temporary suspension shall provide 25 per cent of the financial assurance that the proponent would have been required to provide if the proponent had not complied with the test, (a) within 30 days of the submission of the Notice of Project Status indicating that the project has been placed in temporary suspension; and (b) no later than the first, second and third anniversaries respectively of the date of submission of the Notice of Project Status indicating that the project has been placed in temporary suspension.
Read the REHABILITATION OF LANDS on e-Laws ↗

Made under Mining Act, R.S.O. 1990, c. M.14.