GO Transit Station Funding Act, 2023, S.O. 2023, c. 17, Sched. 2
Section 7
When charge is payable
Cite as GO Transit Station Funding Act, 2023, S.O. 2023, c. 17, Sched. 2, s. 7 · current to November 11, 2026 · consolidated from November 27, 2025 · read from e-Laws on November 17, 2026
The text
(1) A transit station charge is payable for a development upon a building permit being issued for the development.
(2) If a development consists of one building that requires more than one building permit, the transit station charge for the development is payable upon the first building permit being issued.
(3) If a development consists of two or more phases that will not be constructed concurrently and are anticipated to be completed in different years, each phase of the development is deemed to be a separate development for the purposes of this section.
(4) The regulations may provide for transit station charges for rental housing development and institutional development to be payable as set out in the regulations.