LIMITATION PERIODS, O. Reg. 153/23

Section 3

Conflicts

Cite as LIMITATION PERIODS, O. Reg. 153/23, s. 3 · current to November 11, 2026 · consolidated from July 1, 2023 · read from e-Laws on November 16, 2026

The text

(1) The limitation period provided for in section 36.1.1 of the Act prevails over the provisions of any other Act or Regulation. (2) Despite subsection (1), in the event of a conflict between the limitation period provided for in section 36.1.1 of the Act and a limitation period provided for in a provision of a statute or regulation referred to in clause 2 (1) (b), the limitation period that provides the longest time period for a claim to be made prevails.
Read the LIMITATION PERIODS on e-Laws ↗

Made under Electricity Act, 1998, S.O. 1998, c. 15, Sched. A.