Building Broadband Faster Act, 2021, S.O. 2021, c. 2, Sched. 1
Section 7
Application for additional time
Cite as Building Broadband Faster Act, 2021, S.O. 2021, c. 2, Sched. 1, s. 7 · current to November 11, 2026 · consolidated from April 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) If a notice specifies a date, the distributor or transmitter may apply to a judge of the Superior Court of Justice for an order altering the date specified in the notice to a later date. 2022, c. 9, Sched. 1, s. 4.
(2) The distributor or transmitter shall give the proponent such notice of the application as a judge of the Superior Court of Justice directs. 2021, c. 2, Sched. 1, s. 7 (2).
(3) If the judge finds that the physical, technical or other difficulties in complying with the notice require additional time, the judge may make whatever order is appropriate. 2021, c. 2, Sched. 1, s. 7 (3).