(1) The proponent may carry out the early works assessment process only until the notice of publication of the draft environmental impact assessment report has been distributed in accordance with subsection 25 (3). (2) Once the notice of publication of the draft environmental impact assessment report has been distributed, the proponent shall immediately cease the early works assessment process if it is underway. (3) Subsections (1) and (2) do not apply to the early works assessment process for proposed changes pursuant to section 29.
Read the BRADFORD BYPASS PROJECT on e-Laws ↗

Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.