AIR POLLUTION - DISCHARGE OF SULPHUR DIOXIDE FROM NICKEL SMELTING AND REFINING FACILITIES IN THE SUDBURY AREA, O. Reg. 652/21
Section 12
Capture efficiency assessment
Cite as AIR POLLUTION - DISCHARGE OF SULPHUR DIOXIDE FROM NICKEL SMELTING AND REFINING FACILITIES IN THE SUDBURY AREA, O. Reg. 652/21, s. 12 · current to November 11, 2026 · consolidated from September 17, 2021 · read from e-Laws on November 16, 2026
The text
(1) No later than one year after this Regulation first applies to a facility, the owner and the operator of the facility shall ensure that a plan to assess the following, in respect of each building at the facility that has a converter aisle containing a pyrometallurgical vessel, is submitted to the Director:
1. The amount of fugitive emissions discharged from the building, expressed as an emission rate.
2. The capture efficiency of each off-gas collection system in the building.
(2) The plan shall contain the following information in respect of each building referred to in subsection (1):
1. A description of each pyrometallurgical process in the building, including process flow diagrams.
2. A drawing that identifies all openings in the building, including doors, windows, louvres and bays.
3. A list of all management methods used in the building in relation to the discharge of sulphur dioxide.
4. An explanation of the model or method that will be used in the assessment.
5. An indication of the parameters that will be measured in the assessment and the location of each measurement in the building.
6. A description of the range of operating conditions over which the assessment will be performed.
7. An explanation of the calculations that will be used in the assessment, including sample calculations and any assumptions made.
(3) The model or method referred to in paragraph 4 of subsection (2) shall be,
(a) a physical model;
(b) a computational fluid dynamic model; or
(c) a method that incorporates the use of source testing and mass balance calculations.
(4) The Director may, by written notice, extend the date by which the plan is required to be submitted and may require the owner or the operator of the facility, or both, to do any or all of the following:
1. Include additional information in the plan.
2. Make changes to the plan, if the Director is of the opinion that the changes are necessary to carry out an accurate assessment under subsection (1).
3. Carry out the assessment set out in the plan in accordance with the notice and submit the results of the assessment by the date set out in the notice.
4. After the results of the assessment have been submitted, perform additional steps, such as measurements or calculations, if the Director is of the opinion that the additional steps are necessary to carry out an accurate assessment under subsection (1).
5. Submit the results of the additional steps by the date set out in the notice.
(5) The owner and the operator of the facility shall ensure that the Director is notified in writing at least 30 days before any measurement is taken in carrying out the assessment and must give representatives of the Ministry an opportunity to witness each measurement being taken.
(6) Before the Director gives a person a notice under subsection (4), the Director shall give the person a draft of the notice and an opportunity to make written submissions to the Director during the period that ends 30 days after the draft is given.
Read the AIR POLLUTION - DISCHARGE OF SULPHUR DIOXIDE FROM NICKEL SMELTING AND REFINING FACILITIES IN THE SUDBURY AREA on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.