Building Transit Faster Act, 2020, S.O. 2020, c. 12
Section 69
Compensation
Cite as Building Transit Faster Act, 2020, S.O. 2020, c. 12, s. 69 · current to November 11, 2026 · consolidated from November 27, 2025 · read from e-Laws on November 17, 2026
The text
(1) A utility company shall compensate Metrolinx for a loss or expense incurred because the utility company failed to comply with a notice under section 46 or an order under section 50. 2020, c. 12, s. 69 (1).
(2) Metrolinx and the utility company may agree upon the compensation. 2020, c. 12, s. 69 (2).
(3) If no agreement is reached, a claim for compensation under this section shall be determined by the Ontario Land Tribunal on application by Metrolinx. 2020, c. 12, s. 69 (3); 2021, c. 4, Sched. 6, s. 32 (1).
(4) The compensation that Metrolinx is entitled to under subsection (1) does not include,
(a) if the utility company carries out the work, the actual cost of the utility company’s work that is apportioned to Metrolinx under subsection 51 (1) or the actual cost of the utility company’s work that subsection 51 (2) requires Metrolinx to bear; or
(b) if Metrolinx carries out the work under clause 68 (b), Metrolinx’s costs of carrying out the work. 2020, c. 12, s. 69 (4).