ONTARIO LINE PROJECT, O. Reg. 341/20

Section 2

Exemptions

Cite as ONTARIO LINE PROJECT, O. Reg. 341/20, s. 2 · current to November 11, 2026 · consolidated from March 30, 2026 · read from e-Laws on November 16, 2026

The text

(1) The Ontario Line Project, other than early works, is exempt from the Act if Metrolinx complies with the Ontario Line project assessment process. O. Reg. 341/20, s. 2 (1); O. Reg. 853/21, s. 1 (1); O. Reg. 59/24, s. 2 (1). (2) Early works are exempt from the Act if Metrolinx complies with the early works assessment process. O. Reg. 341/20, s. 2 (2); O. Reg. 853/21, s. 1 (1); O. Reg. 59/24, s. 2 (1). (3) Subsections 15.1.2 (2) and (6) and 17.27 (2) and (6) of the Act do not apply to, (a) the Minister of the Environment, Conservation and Parks with respect to any permit that Minister may issue under section 22 of the Species Conservation Act, 2025 related to the Ontario Line Project; and (b) the Minister of Heritage, Sport, Tourism and Culture Industries with respect to any consent that Minister may issue for the purpose of compliance with subsection 25.2 (6) of the Ontario Heritage Act related to the Ontario Line Project. O. Reg. 341/20, s. 2 (3); O. Reg. 853/21, s. 1 (2); O. Reg. 59/24, s. 2 (2); O. Reg. 66/26, s. 1.
Read the ONTARIO LINE PROJECT on e-Laws ↗

Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.