ONTARIO LINE PROJECT, O. Reg. 341/20
Section 11
Final early works report
Cite as ONTARIO LINE PROJECT, O. Reg. 341/20, s. 11 · current to November 11, 2026 · consolidated from March 30, 2026 · read from e-Laws on November 16, 2026
The text
(1) Within 65 days of publishing the notice of publication of the draft early works report pursuant to clause 9 (4) (b), Metrolinx shall,
(a) complete the consultation and issues resolution process under section 10;
(b) update the draft early works report, including by adding,
(i) a description of the issues resolution process employed by Metrolinx in respect of any concerns raised by Indigenous communities and interested persons,
(ii) a description of the concerns raised by Indigenous communities and interested persons in the issues resolution process and of the outcome of the process, including what, if anything, Metrolinx did or will do in respect of the concerns raised, and
(iii) a description of any impacts to the timeline for implementation of the early works as a result of how Metrolinx has addressed the concerns; and
(c) publish the final early works report on its website.
(2) Metrolinx shall ensure that all of the persons and Indigenous communities to whom a copy of the notice under clause 9 (4) (a) is given are notified of the publication of the final early works report and are provided with access to a copy of it.
Read the ONTARIO LINE PROJECT on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.