Ontario Fair Hydro Plan Act, 2017, S.O. 2017, c. 16, Sched. 1
Section 1.5
Protection against liability of IESO
Cite as Ontario Fair Hydro Plan Act, 2017, S.O. 2017, c. 16, Sched. 1, s. 1.5 · current to November 11, 2026 · consolidated from January 1, 2022 · read from e-Laws on November 17, 2026
The text
(1) Nothing in this Act or in any contract or instrument shall be interpreted so as to create, continue or impose liability on the IESO in favour of any person for or in respect of any amount determined to be, or to form part of, a clean energy adjustment under this Act as it read immediately before the final plan date, including for or in respect of,
(a) collecting, receiving, holding, applying, depositing or remitting such an amount;
(b) reporting on such an amount; or
(c) servicing, administering or enforcing any collections or remittances of such an amount. 2019, c. 6, Sched. 3, s. 2.
(2) The IESO is not required to comply with any requirement under any contract or instrument that provides for the administration or servicing of the investment asset on behalf of the Fair Hydro Trust, including any requirement to,
(a) collect, receive, hold, apply, deposit or remit a clean energy adjustment under this Act as it read immediately before the final plan date;
(b) report on or provide notice on a clean energy adjustment under this Act as it read immediately before the final plan date;
(c) service, administer or enforce,
(i) a clean energy adjustment under this Act as it read immediately before the final plan date, or
(ii) any collections or remittances of a clean energy adjustment under this Act as it read immediately before the final plan date; or
(d) develop and implement an implementation plan in respect of obligations that would arise in the future under this Act as it read immediately before the final plan date. 2019, c. 6, Sched. 3, s. 2.
(3) This section does not affect the validity of any transfer of the investment asset to the Fair Hydro Trust or the application of each of the following in accordance with the terms of each of the following, in relation to such a transfer:
1. Any representation or certification made by the IESO to the Fair Hydro Trust or to or in favour of any beneficiary or any secured party.
2. Any warranty, acknowledgment or indemnity given by the IESO to the Fair Hydro Trust or to or in favour of any beneficiary or any secured party.
3. Any restrictive covenant agreed to by the IESO to the Fair Hydro Trust or to or in favour of any beneficiary or any secured party. 2019, c. 6, Sched. 3, s. 2.
(4) Nothing in this Act or in any contract or instrument shall be interpreted so as to create, continue or impose liability on the IESO to pay the Fair Hydro Trust the carrying costs determined under section 9.1 of the General Regulation as it read immediately before the final plan date. 2019, c. 6, Sched. 3, s. 2.
(5) Any right or obligation of the IESO to make or receive a payment, an adjustment or an amount to or from an electricity vendor, a unit sub-meter provider or another person, that relates to the rates applicable to a specified consumer, a regulated rate consumer or a consumer who meets the prescribed requirements and that is to be provided by or under this Act as it read immediately before the final plan date is subject to the limitation period provided for in the regulations, if any. 2021, c. 34, Sched. 9, s. 12 (6).
Read the Ontario Fair Hydro Plan Act, 2017 on e-Laws ↗