(1) The amount of the school renewal allocation for a district school board for the fiscal year is the sum of the following amounts:
1. The amount determined under subsection (2), multiplied by one-third.
2. The amount determined under subsection (3), multiplied by two-thirds.
3. The capital renewal amount set out in Column 2 of Table 28.1 opposite the name of the board.
4. The maintenance (operating) amount set out in Column 3 of Table 28.1 opposite the name of the board. O. Reg. 215/16, s. 50 (1); O. Reg. 438/16, s. 5.
(2) The amount referred to in paragraph 1 of subsection (1) is determined as follows:
1. Take the percentage of the total elementary school area of the board that relates to buildings that are less than 20 years old, set out in Column 2 of Table 29 opposite the name of the board.
2. Apply the percentage referred to in paragraph 1 to the benchmark renewal cost per metre squared of $7.59.
3. Take the percentage of the total elementary school area of the board that relates to buildings that are 20 years old or older, set out in Column 3 of Table 29 opposite the name of the board.
4. Apply the percentage referred to in paragraph 3 to the benchmark renewal cost per metre squared of $11.38.
5. Add the amounts obtained under paragraphs 2 and 4 to obtain a weighted average benchmark elementary school renewal cost per metre squared.
6. Multiply the amount obtained under paragraph 5 by the adjusted elementary school area requirement for the board determined under paragraph 3 of subsection 49 (2).
7. Take the percentage of the total secondary school area of the board that relates to buildings that are less than 20 years old, set out in Column 4 of Table 29 opposite the name of the board.
8. Apply the percentage referred to in paragraph 7 to the benchmark renewal cost per metre squared of $7.59.
9. Take the percentage of the total secondary school area of the board that relates to buildings that are 20 years old or older, set out in Column 5 of Table 29 opposite the name of the board.
10. Apply the percentage referred to in paragraph 9 to the benchmark renewal cost per metre squared of $11.38.
11. Add the amounts obtained under paragraphs 8 and 10 to obtain a weighted average benchmark secondary school renewal cost per metre squared.
12. Multiply the amount obtained under paragraph 11 by the adjusted secondary school area requirement for the board determined under paragraph 14 of subsection 49 (2).
13. Multiply the amount obtained under paragraph 11 by the adjusted continuing education and other programs area requirement for the board determined under paragraph 11 of subsection 49 (2).
14. Identify each school of the board that meets the following criteria:
i. The school is identified as an elementary school in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3).
ii. The school opened and began operating before September 1, 2011.
iii. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 15 ii or the predecessor of subparagraph 15 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per elementary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $1,921.46.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
15. For each school of the board identified under paragraph 14, calculate a top-up amount for school renewal as follows:
i. Determine the 2016-2017 enrolment.
ii. Determine the capacity of the school, in terms of pupil places, in accordance with subsection 61 (3). However, the capacity of a school, for which the number determined under subparagraph i is zero, is deemed, for the purposes of this paragraph, to be zero.
iii. Multiply the number determined under subparagraph i by the benchmark area requirement per pupil of 9.7 metres squared.
iv. Multiply the number determined under subparagraph iii by the weighted average benchmark elementary school renewal cost per metre squared, as determined for the board under paragraph 5.
v. Multiply the number determined under subparagraph iv by the supplementary elementary school area factor set out in Column 2 of Table 23 opposite the name of the board.
vi. Multiply the capacity of the school, in terms of pupil places, as determined under subparagraph ii, by the benchmark area requirement per pupil of 9.7 metres squared.
vii. Multiply the number determined under subparagraph vi by the weighted average benchmark elementary school renewal cost per metre squared, as determined for the board under paragraph 5.
viii. Multiply the number determined under subparagraph vii by the supplementary elementary school area factor set out in Column 2 of Table 23 opposite the name of the board.
ix. Multiply the amount determined under subparagraph viii by 0.95.
x. Divide the number determined under subparagraph i by the number determined under subparagraph ii. If the number determined for the purposes of subparagraph ii is zero, the number determined for the purposes of this subparagraph shall be zero.
xi. If the number determined under subparagraph x is less than or equal to 0.65, multiply the amount determined under subparagraph viii by 0.10.
xii. If the number determined under subparagraph x is greater than 0.65, multiply the amount determined under subparagraph viii by 0.15.
xiii. Subtract the amount determined under subparagraph v from the amount determined under subparagraph ix.
xiv. Take the lesser of the amount determined under subparagraph xi or xii, as the case may be, and the amount determined under subparagraph xiii to obtain the top-up amount for school renewal for the elementary school. However, if the amount determined under subparagraph xiii is zero or negative or if the number determined under subparagraph i is zero, the top-up amount for school renewal for the elementary school is zero.
16. Total the top-up amounts for school renewal determined under paragraph 15 for each elementary school of the board.
17. Identify each rural elementary school of the board that meets the following criteria:
i. The school is not an outlying elementary school facility of the board.
ii. The school opened and began operating before September 1, 2011.
iii. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 15 ii or the predecessor of subparagraph 15 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per elementary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $1,921.46.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
18. For each rural elementary school of the board identified under paragraph 17, subtract the amount determined under subparagraph 15 v from the amount determined under subparagraph 15 viii.
19. Total the amounts determined under paragraph 18. If the number determined for a school under subparagraph 15 i is zero, or if the amount determined for the school under paragraph 18 is negative, the amount determined for the school under paragraph 18 is deemed to be zero for the purposes of this paragraph.
20. Total the amounts determined under subparagraph 15 xiv for the rural elementary schools of the board identified in paragraph 17.
21. Subtract the amount determined under paragraph 20 from the amount determined under paragraph 19.
22. For each outlying elementary school facility of the board that meets the criteria set out in subparagraphs 17 ii and iii, subtract the amount determined under subparagraph 15 v from the amount determined under subparagraph 15 viii.
23. Total the amounts determined under paragraph 22. If the number determined for a school under subparagraph 15 i is zero, or if the amount determined for the school under paragraph 22 is negative, the amount determined for the school under paragraph 22 is deemed to be zero for the purposes of this paragraph.
24. Total the amounts determined under subparagraph 15 xiv for the outlying elementary school facilities of the board.
25. Subtract the amount determined under paragraph 24 from the amount determined under paragraph 23.
26. Identify each school of the board that meets the following criteria:
i. The school is identified as a secondary school in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3).
ii. The school opened and began operating before September 1, 2011.
iii. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 27 ii or the predecessor of subparagraph 27 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per secondary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $2,096.16.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
27. For each school of the board identified under paragraph 26, calculate a top-up amount for school renewal as follows:
i. Determine the 2016-2017 enrolment.
ii. Determine the capacity of the school, in terms of pupil places, in accordance with subsection 61 (4). However, the capacity of a school, for which the number determined under subparagraph i is zero, is deemed, for the purposes of this paragraph, to be zero.
iii. Multiply the number determined under subparagraph i by the benchmark area requirement per pupil of 12.07 metres squared.
iv. Multiply the number determined under subparagraph iii by the weighted average benchmark secondary school renewal cost per metre squared, as determined for the board under paragraph 11.
v. Multiply the number determined under subparagraph iv by the supplementary secondary school area factor set out in Column 3 of Table 23 opposite the name of the board.
vi. Multiply the capacity of the school, in terms of pupil places, as determined under subparagraph ii, by the benchmark area requirement per pupil of 12.07 metres squared.
vii. Multiply the number determined under subparagraph vi by the weighted average benchmark secondary school renewal cost per metre squared, as determined for the board under paragraph 11.
viii. Multiply the amount determined under subparagraph vii by the supplementary secondary school area factor set out in Column 3 of Table 23 opposite the name of the board.
ix. Multiply the amount determined under subparagraph viii by 0.95.
x. Divide the number determined under subparagraph i by the number determined under subparagraph ii. If the number determined for the purposes of subparagraph ii is zero, the number determined for the purposes of this subparagraph shall be zero.
xi. If the number determined under subparagraph x is less than or equal to 0.65, multiply the amount determined under subparagraph viii by 0.10.
xii. If the number determined under subparagraph x is greater than 0.65, multiply the amount determined under subparagraph viii by 0.15.
xiii. Subtract the amount determined under subparagraph v from the amount determined under subparagraph ix.
xiv. Take the lesser of the amount determined under subparagraph xi or xii, as the case may be, and the amount determined under subparagraph xiii to obtain the top-up amount for school renewal for the secondary school. However, if the amount determined under subparagraph xiii is zero or negative or if the number determined under subparagraph i is zero, the top-up amount for school renewal for the secondary school is zero.
28. Total the top-up amounts for school renewal determined under paragraph 27 for each secondary school of the board.
29. Identify each rural secondary school of the board that meets the following criteria:
i. The school is not an outlying secondary school facility of the board.
ii. The school opened and began operating before September 1, 2011.
iii. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 27 ii or the predecessor of subparagraph 27 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per secondary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $2,096.16.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
30. For each rural secondary school of the board identified under paragraph 29, subtract the amount determined under subparagraph 27 v from the amount determined under subparagraph 27 viii.
31. Total the amounts determined under paragraph 30. If the number determined for a school under subparagraph 27 i is zero, or if the amount determined for the school under paragraph 30 is negative, the amount determined for the school under paragraph 30 is deemed to be zero for the purposes of this paragraph.
32. Total the amounts determined under subparagraph 27 xiv for the rural secondary schools of the board identified in paragraph 29.
33. Subtract the amount determined under paragraph 32 from the amount determined under paragraph 31.
34. For each outlying secondary school facility of the board that meets the criteria set out in subparagraphs 29 ii and iii, subtract the amount determined under subparagraph 27 v from the amount determined under subparagraph 27 viii.
35. Total the amounts determined under paragraph 34. If the number determined for a school under subparagraph 27 i is zero, or if the amount determined for the school under paragraph 34 is negative, the amount determined for the school under paragraph 34 is deemed to be zero for the purposes of this paragraph.
36. Total the amounts determined under subparagraph 27 xiv for the outlying secondary school facilities of the board.
37. Subtract the amount determined under paragraph 36 from the amount determined under paragraph 35.
38. Take the amount for school renewal enhancement set out opposite the name of the board in Table 30.
39. Total the amounts determined under paragraphs 6, 12, 13, 16, 21, 25, 28, 33, 37 and 38.
40. Multiply the sum determined under paragraph 39 by the geographic adjustment factor specified for the board in Column 2 of Table 24.
(3) The amount referred to in paragraph 2 of subsection (1) is determined as follows:
1. Take the percentage of the total elementary school area of the board that relates to buildings that are less than 20 years old, set out in Column 2 of Table 31 opposite the name of the board.
2. Apply the percentage referred to in paragraph 1 to the benchmark renewal cost per metre squared of $7.89.
3. Take the percentage of the total elementary school area of the board that relates to buildings that are 20 years old or older, set out in Column 3 of Table 31 opposite the name of the board.
4. Apply the percentage referred to in paragraph 3 to the benchmark renewal cost per metre squared of $11.83.
5. Add the amounts obtained under paragraphs 2 and 4 to obtain a weighted average benchmark elementary school renewal cost per metre squared.
6. Multiply the amount obtained under paragraph 5 by the adjusted elementary school area requirement for the board determined under paragraph 3 of subsection 49 (3).
7. Take the percentage of the total secondary school area of the board that relates to buildings that are less than 20 years old, set out in Column 4 of Table 31 opposite the name of the board.
8. Apply the percentage referred to in paragraph 7 to the benchmark renewal cost per metre squared of $7.89.
9. Take the percentage of the total secondary school area of the board that relates to buildings that are 20 years old or older, set out in Column 5 of Table 31 opposite the name of the board.
10. Apply the percentage referred to in paragraph 9 to the benchmark renewal cost per metre squared of $11.83.
11. Add the amounts obtained under paragraphs 8 and 10 to obtain a weighted average benchmark secondary school renewal cost per metre squared.
12. Multiply the amount obtained under paragraph 11 by the adjusted secondary school area requirement for the board determined under paragraph 14 of subsection 49 (3).
13. Multiply the amount obtained under paragraph 11 by the adjusted continuing education and other programs area requirement for the board determined under paragraph 11 of subsection 49 (3).
14. Identify each school of the board that meets the following criteria:
i. The school is identified as an elementary school in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3).
ii. The school is located at least 10 kilometres from every other elementary or secondary school, identified as such in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3), that is located on a different campus and has a 2016-2017 enrolment that is greater than zero.
iii. The school opened and began operating before September 1, 2011.
iv. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 15 ii or the predecessor of subparagraph 15 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per elementary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $1,921.46.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
15. For each school of the board identified under paragraph 14, calculate a top-up amount for school renewal as follows:
i. Determine the 2016-2017 enrolment.
ii. Determine the capacity of the school, in terms of pupil places, in accordance with subsection 61 (3). However, the capacity of a school, for which the number determined under subparagraph i is zero, is deemed, for the purposes of this paragraph, to be zero.
iii. Subtract the number determined under subparagraph i from the number determined under subparagraph ii. If the result is negative, it is deemed to be zero.
iv. Multiply the number determined under subparagraph iii by the benchmark area requirement per pupil of 9.7 metres squared.
v. Multiply the number determined under subparagraph iv by the weighted average benchmark elementary school renewal cost per metre squared, as determined for the board under paragraph 5.
vi. Multiply the amount determined under subparagraph v by the supplementary elementary school area factor set out in Column 2 of Table 27 opposite the name of the board.
16. Total the top-up amounts for school renewal determined under paragraph 15 for each elementary school of the board.
17. Identify each school of the board that meets the following criteria:
i. The school is identified as a secondary school in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3).
ii. The school is located at least 20 kilometres from every other secondary school, identified as such in accordance with the document entitled “User Guide for the School Facilities Inventory System Application”, dated November 2009, which is available as described in subsection 3 (3), that is located on a different campus and has a 2016-2017 enrolment that is greater than zero.
iii. The school opened and began operating before September 1, 2011.
iv. If the school has been the subject of an addition, alteration, renovation or major repair project that was completed on or after September 1, 2011, the total construction costs incurred by the board for the project, less any insurance proceeds received by the board in respect of the project, did not exceed the following amount:
A. Take the number determined under subparagraph 18 ii or the predecessor of subparagraph 18 ii in the grant regulation for the fiscal year in which the construction began, multiplied by the variable area per secondary pupil for the school.
B. Multiply the number determined under sub-subparagraph A by $2,096.16.
C. Multiply the amount determined under sub-subparagraph B by the site specific geographic adjustment factor for the school.
D. Multiply the amount determined under sub-subparagraph C by 0.5.
18. For each school of the board identified under paragraph 17, calculate a top-up amount for school renewal as follows:
i. Determine the 2016-2017 enrolment.
ii. Determine the capacity of the school, in terms of pupil places, in accordance with subsection 61 (4). However, the capacity of a school, for which the number determined under subparagraph i is zero, is deemed, for the purposes of this paragraph, to be zero.
iii. Subtract the number determined under subparagraph i from the number determined under subparagraph ii. If the result is negative, it is deemed to be zero.
iv. Multiply the number determined under subparagraph iii by the benchmark area requirement per pupil of 12.07 metres squared.
v. Multiply the number determined under subparagraph iv by the weighted average benchmark secondary school renewal cost per metre squared, as determined for the board under paragraph 11.
vi. Multiply the number determined under subparagraph v by the supplementary secondary school area factor set out in Column 3 of Table 27 opposite the name of the board.
19. Total the top-up amounts for school renewal determined under paragraph 18 for each secondary school of the board.
20. Take the amount for school renewal enhancement set out opposite the name of the board in Table 30.
21. Total the amounts determined under paragraphs 6, 12, 13, 16, 19 and 20.
22. Multiply the sum determined under paragraph 21 by the geographic adjustment factor specified for the board in Column 2 of Table 28.