Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4
Section 7
Application
Cite as Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4, s. 7 · current to November 11, 2026 · consolidated from December 4, 2024 · read from e-Laws on November 17, 2026
The text
(1) This section applies with respect to the following excavation or dig projects:
1. A designated broadband project.
2. An excavation or dig project that satisfies such criteria as may be prescribed by the Minister.
3. An excavation or dig project for which the project owner chooses to use a dedicated locator. 2022, c. 9, Sched. 2, s. 6 (1).
(2) Subject to subsections (3) and (4), a project owner who intends to carry out a project referred to in subsection (1) shall notify the Corporation of the project at least 90 days before any excavation or dig is expected to commence. 2022, c. 9, Sched. 2, s. 6 (1).
(3) The Corporation may permit a project owner to give the notice under subsection (2) less than 90 days before any excavation or dig is expected to commence. 2022, c. 9, Sched. 2, s. 6 (1).
(4) If so directed by the Minister of Infrastructure, the Corporation shall permit a project owner of a designated broadband project to give the notice under subsection (2) less than 90 days before any excavation or dig is expected to commence. 2022, c. 9, Sched. 2, s. 6 (1).
(5) The notice under subsection (2) shall include such information as the Corporation may require and the project owner shall update the information 90 days after the notice is given and every 90 days thereafter until the conclusion of the project. 2022, c. 9, Sched. 2, s. 6 (1).
(5.1) For greater certainty, a notification given under subsection (2) is not a locate request and the project owner shall pay any fee set under clause 4 (1) (b) in relation to such notification. 2024, c. 1, s. 9 (1).
(6) If the Corporation receives a notice under subsection (2), the Corporation shall notify all affected members of the Corporation of the notice within three business days, or such other time period as may be prescribed by the Minister, after receiving the notice. 2022, c. 9, Sched. 2, s. 6 (1).
(6.1) Within 10 business days after receiving the notice under subsection (6), an affected member may submit a request to the Corporation to be approved to respond to notifications made by the Corporation under subsection (9.1) respecting the member’s own underground infrastructure. 2024, c. 28, Sched. 22, s. 1 (1).
(6.2) If an affected member has submitted a request to the Corporation pursuant to subsection (6.1), the Corporation shall consider the request, having regard to,
(a) safety concerns;
(b) the specialized nature of the affected member’s infrastructure;
(c) any limitations regarding the affected member’s mapping information; and
(d) any other factors that may be prescribed by the Minister. 2024, c. 28, Sched. 22, s. 1 (1).
(6.3) Within 15 business days of receiving the request under subsection (6.1), the Corporation shall make a determination and provide written notice of the determination to the affected member, the project owner and any other affected member with respect to the project. 2024, c. 28, Sched. 22, s. 1 (1).
(6.4) A determination made under subsection (6.3) is final and there is no right to appeal that decision. 2024, c. 28, Sched. 22, s. 1 (1).
(6.5) The following requirements apply once the Corporation has made a determination under subsection (6.3):
1. In the case that the Corporation approves a request made by a member under subsection (6.1),
i. the member ceases to be an affected member for the purposes of this section, and
ii. the project owner and any remaining affected members shall comply with subsection (7) within 10 business days of receiving the notice under subsection (6.3).
2. In the case that the Corporation denies a request by a member made under subsection (6.1),
i. the member continues to be an affected member for the purposes of this section, and
ii. the project owner and the affected members shall comply with subsection (7) within 10 business days of receiving the notice under subsection (6.3). 2024, c. 28, Sched. 22, s. 1 (1).
(7) Within 10 business days after receiving the notice under subsection (6) or, if a request is made under subsection (6.1), in accordance with the timing set out in subsection (6.5),
(a) the project owner and any affected members who have not made a request under subsection (6.1) or who have received notice that their request has been denied under subsection (6.3) shall agree in writing on a locator who will respond to all notifications made by the Corporation under clause (9.1) (a) in respect of the project; and
(b) the affected members shall give to the dedicated locator mapping information, such as the location of the member’s underground infrastructure, and any other information that the dedicated locator considers necessary. 2022, c. 9, Sched. 2, s. 6 (1); 2024, c. 1, s. 9 (2); 2024, c. 28, Sched. 22, s. 1 (2, 3).
(8) The time limit set out in subsection (7) shall not apply and a different time limit shall apply if the affected members and the project owner agree in writing to a different time limit. For clarity, the agreed upon time limit may relate to either or both the things required by subsection (7). 2022, c. 9, Sched. 2, s. 6 (1).
(9) After the dedicated locator has been agreed upon in respect of a project, the project owner shall promptly notify the Corporation of the name and contact information of the dedicated locator. 2022, c. 9, Sched. 2, s. 6 (1).
(9.1) If the Corporation receives a dedicated locator request with regard to a project referred to in subsection (1), the Corporation shall notify,
(a) the dedicated locator set out in the notification given to the Corporation in respect of the project under subsection (9);
(b) if the excavation or dig set out in the dedicated locator request may affect transmission infrastructure owned or operated by a member of the Corporation, each member whose transmission infrastructure may be affected; and
(c) if the excavation or dig set out in the dedicated locator request may affect underground infrastructure owned or operated by a member of the Corporation whose request was approved under subsection (6.3), each member whose infrastructure may be affected. 2024, c. 1, s. 9 (3); 2024, c. 28, Sched. 22, s. 1 (4).
(10) Within 10 business days after a dedicated locator receives a notification under clause (9.1) (a) in respect of a dedicated locator request, the dedicated locator shall do either of the following with respect to each affected member’s underground infrastructure:
1. Mark on the ground the location of the member’s underground infrastructure and provide a written document containing information respecting the location of the underground infrastructure.
2. State in writing that none of the member’s underground infrastructure will be affected by the excavation or dig. 2022, c. 9, Sched. 2, s. 6 (1); 2024, c. 1, s. 9 (4).
(11) The time limit set out in subsection (10) shall not apply and a different time limit shall apply if the project owner and dedicated locator agree in writing to another time limit and, if a different time limit is agreed to, the project owner shall promptly notify the Corporation of the different time limit. 2022, c. 9, Sched. 2, s. 6 (1).
(12) For the purposes of subsections (6), (7), (8) and (10), a reference to “affected members” includes a member that owns or operates transmission infrastructure only if the member also owns or operates other underground infrastructure and a reference to the affected member’s underground infrastructure does not include the affected member’s transmission infrastructure. 2022, c. 9, Sched. 2, s. 6 (1); 2024, c. 1, s. 9 (5).
(13) If a member of the Corporation receives notification under clause (9.1) (b) or (c) with regard to a project referred to in subsection (1), the following rules apply:
1. If the locate request referred to in subsection (9.1) would have been a specified request if it had been submitted by an excavator who was not a project owner, the member shall do the things required by subsection 6 (1) in respect of the infrastructure within the time limits set out in subsection 6 (2).
2. If the locate request referred to in subsection (9.1) would have been a standard request if it had been submitted by an excavator who was not a project owner, the member shall do the things required by subsection 6 (1) in respect of the infrastructure within the time limits set out in subsection 6 (3) or (5), as applicable. 2024, c. 1, s. 9 (6); 2024, c. 28, Sched. 22, s. 1 (5, 6).
(14) The project owner shall bear the costs of the dedicated locator. 2022, c. 9, Sched. 2, s. 6 (1).
(15) A member who receives a notification in respect of a locate request under clause (9.1) (b) or (c) shall not charge a fee in respect of doing either of the things required under subsection 6 (1) in accordance with subsection (13) of this section. 2024, c. 1, s. 9 (7); 2024, c. 28, Sched. 22, s. 1 (7).
Read the Ontario Underground Infrastructure Notification System Act, 2012 on e-Laws ↗