Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4

Section 2.5

Conditions precedent

Cite as Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4, s. 2.5 · current to November 11, 2026 · consolidated from December 4, 2024 · read from e-Laws on November 17, 2026

The text

The Minister may exercise the power under subsection 2.3 (1) or any other prescribed provision only if the Minister is of the opinion that it is advisable to exercise the power in the public interest because at least one of the following conditions is satisfied: 1. The exercise of the power is necessary to prevent serious harm to underground infrastructure, public safety or to the interests of the public. 2. An event of force majeure has occurred. 3. The Corporation is facing a risk of insolvency. 4. The number of members of the board of directors of the Corporation is insufficient for a quorum. 2022, c. 21, Sched. 8, s. 2.
Read the Ontario Underground Infrastructure Notification System Act, 2012 on e-Laws ↗