Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4
Section 10
Commencement of excavation or dig
Cite as Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4, s. 10 · current to November 11, 2026 · consolidated from December 4, 2024 · read from e-Laws on November 17, 2026
The text
(1) An excavator shall not commence an excavation or dig unless either of the following conditions are satisfied:
1. All of the following apply:
i. The excavator has submitted a locate request.
ii. Each member that owns or operates underground infrastructure that may be affected by an excavation or dig has done the things required by subsection 6 (1) or, if section 7 applies in respect of the excavation or dig, the dedicated locator has done the things required by subsection 7 (10) and, if applicable, each member who owns or operates transmission infrastructure has complied with subsection 7 (13).
iii. If locates are provided, the excavator has ensured that the locate markings on the ground do not conflict with the written information provided respecting the underground infrastructure.
2. The excavator,
i. has received from another excavator the information referred to in paragraph 1 or 2 of subsection 6 (1) pertaining to the same excavation or dig parameters as the excavator’s own excavation or dig, including the geographical limits of the area subject to the locate request, in accordance with section 11, and
ii. if locates were provided, has ensured that the markings on the ground do not conflict with the written information provided respecting the underground infrastructure. 2022, c. 9, Sched. 2, s. 6 (1).
(2) An excavator shall not continue an excavation or dig after the expiry of the validity period of a locate unless any of the following circumstances exist:
1. The excavator has submitted a new locate request and subparagraphs 1 ii and iii of subsection (1) of this section have been satisfied in respect of the new locate request.
2. The excavator,
i. has received from another excavator the information referred to in paragraph 1 or 2 of subsection 6 (1) pertaining to the same excavation or dig parameters as the excavator’s own excavation or dig, including the geographical limits of the area subject to the locate request, in accordance with section 11, and
ii. if locates were provided, has ensured that the markings on the ground do not conflict with the written information provided respecting the underground infrastructure.
3. Such other circumstances as may be prescribed by the Minister. 2022, c. 9, Sched. 2, s. 6 (1); 2024, c. 1, s. 10.
Read the Ontario Underground Infrastructure Notification System Act, 2012 on e-Laws ↗