APPLICATIONS FOR ENVIRONMENTAL COMPLIANCE APPROVALS, O. Reg. 255/11

Section 2

Application requirements; s. 20.2 (4) of the Act

Cite as APPLICATIONS FOR ENVIRONMENTAL COMPLIANCE APPROVALS, O. Reg. 255/11, s. 2 · current to November 11, 2026 · consolidated from October 31, 2011 · read from e-Laws on November 17, 2026

The text

(1) For the purposes of subsection 20.2 (4) of the Act, the following are requirements for an application under subsection 20.2 (1) or (2) of the Act for approval to engage in an activity: 1. The application must include an application form, the applicable portions of which have been completed by the applicant, that is available on a website maintained by the Ministry on the Internet and that requires information the Director considers relevant to the application. 2. The application must include a project description for the activity that complies with Schedule 1. 3. The application must include an executive summary of the material required by paragraph 2. 4. The application must include a description of the ownership of the land where the applicant will engage in the activity, and, if the applicant does not own the land, a document signed by the owner indicating that the applicant has the authority to engage in the activity on the land. 5. The application must include a description of the current land uses of the land where the applicant will engage in the activity, and of any land adjacent to that land. 6. If the activity will be part of a larger undertaking carried out by the applicant, the application must include a description of the current land uses of the land where the applicant carries on the undertaking, and of any land adjacent to that land. 7. The application must include a description of the uses for which the land referred to in paragraph 5 or 6, and any land adjacent to that land, are zoned under any applicable zoning by-law made under the Planning Act. 8. If a municipality makes a map available that shows the uses for which land referred to in paragraph 5 or 6 are zoned under a zoning by-law made under the Planning Act, the application must include a copy of that map. 9. If the activity involves the use or operation of mobile equipment, the application must include a drawing that shows how the mobile equipment is typically configured when it is used or operated. 10. If the activity is the use, operation, establishment, alteration, extension or replacement of new or existing sewage works for the collection or transmission of sewage, the application must include a site plan that shows the following: i. The area where the works will be used, operated, established, altered, extended or replaced, expressed with reference to municipal addresses, if applicable. ii. Any municipal boundary that crosses the area where the works will be used, operated, established, altered, extended or replaced. iii. Any boundary of the Lake Simcoe watershed, the Niagara Escarpment Planning Area, the Oak Ridges Moraine Area or the Protected Countryside that is within 125 metres of the area where the works will be used, operated, established, altered, extended or replaced. 11. If paragraphs 9 and 10 do not apply and the activity is part of a larger undertaking that is carried on by the applicant, the application must include a site plan of the site of the undertaking that the activity is part of that shows the following: i. The boundary of the site of the undertaking, including geographic coordinates for all points that are necessary to accurately describe the boundary. ii. The locations of buildings and other structures, roads, railway tracks, utility corridors, paved areas, bermed areas, site fencing and pollution control devices. iii. In the case of an activity mentioned in subsection 9 (1) of the Act, the location of any plant, structure, equipment, apparatus, mechanism or thing that may discharge or from which may be discharged a contaminant into any part of the natural environment other than water. iv. In the case of an activity mentioned in subsection 27 (1) of the Act that relates to a waste management system, the location of any thing, other than a vehicle, that may deposit, dispose of, handle, store, transfer, treat or process waste. v. In the case of an activity mentioned in subsection 27 (1) of the Act that relates to a waste disposal site, the location of, A. any land upon, into, in or through which, or building or structure in which, waste will be deposited, disposed of, handled, stored, transferred, treated or processed, and B. any machinery or equipment, other than vehicles, used in connection with the depositing, disposal, handling, storage, transfer, treatment or processing referred to in sub-subparagraph A. vi. In the case of an activity mentioned in subsection 53 (1) of the Ontario Water Resources Act, the location of any sewage works. vii. Any municipal boundary that crosses the boundary of the site of the undertaking. viii. Any boundary of the Lake Simcoe watershed, the Niagara Escarpment Planning Area, the Oak Ridges Moraine Area or the Protected Countryside that is within 125 metres of the site of the undertaking. ix. The location of the activity, indicated by a conspicuous arrow, circle or other marking. 12. If paragraphs 9 and 10 do not apply and the activity is not part of a larger undertaking that is carried on by the applicant, the application must include a site plan of the site of the activity that shows the following: i. The boundary of the site of the activity, including geographic coordinates for all points that are necessary to accurately describe the boundary. ii. The locations of buildings and other structures, roads, railway tracks, utility corridors, paved areas, bermed areas, site fencing and pollution control devices. iii. In the case of an activity mentioned in subsection 9 (1) of the Act, the location of any plant, structure, equipment, apparatus, mechanism or thing that may discharge or from which may be discharged a contaminant into any part of the natural environment other than water. iv. In the case of an activity mentioned in subsection 27 (1) of the Act that relates to a waste management system, the location of any thing, other than a vehicle, that may deposit, dispose of, handle, store, transfer, treat or process waste. v. In the case of an activity mentioned in subsection 27 (1) of the Act that relates to a waste disposal site, the location of, A. any land upon, into, in or through which, or building or structure in which, waste will be deposited, disposed of, handled, stored, transferred, treated or processed, and B. any machinery or equipment, other than vehicles, used in connection with the depositing, disposal, handling, storage, transfer, treatment or processing referred to in sub-subparagraph A. vi. In the case of an activity mentioned in subsection 53 (1) of the Ontario Water Resources Act, the location of any sewage works. vii. Any municipal boundary that crosses the boundary of the site of the activity. viii. Any boundary of the Lake Simcoe watershed, the Niagara Escarpment Planning Area, the Oak Ridges Moraine Area or the Protected Countryside that is within 125 metres of the site of the activity. 13. If the Financial Assurance Guideline indicates that financial assurance should normally be required or financial assurance is required by Ontario Regulation 232/98 (Landfilling Sites) made under the Act, i. the application must include a financial assurance estimate prepared in accordance with the Guideline, and ii. the application must include the reasons why the amount of the estimate is sufficient for the purposes for which the financial assurance is given. 14. The application must include a list, including any unique document identifiers issued by the Ministry, of any approvals, orders or other instruments issued under the Act, the Environmental Assessment Act, the Ontario Water Resources Act or the Safe Drinking Water Act, 2002 that, i. are relevant to the application, and ii. are held by or were issued to the applicant or are being requested by the applicant. O. Reg. 255/11, s. 2 (1). (2) Paragraphs 4 to 8 of subsection (1) do not apply if the activity involves the use or operation of mobile equipment. O. Reg. 255/11, s. 2 (2). (3) Paragraphs 4 to 9, 11 and 12 of subsection (1) do not apply if the activity is using, operating, establishing, altering, enlarging or extending a waste management system that collects, handles and transports waste but does not store, process or dispose of waste. O. Reg. 255/11, s. 2 (3). (4) For the purposes of subsection 20.2 (4) of the Act, the following are additional requirements for an application under subsection 20.2 (1) or (2) of the Act for approval to engage in an activity: 1. Every drawing, map or site plan that is included in the application must show the relative sizes of things and must contain a legend. 2. Every map or site plan that is included in the application must contain a north arrow. 3. If a document that is included in the application was prepared expressly for the purpose of the application and contains a measurement expressed in units other than metric units, the measurement must also be expressed in metric units. O. Reg. 255/11, s. 2 (4). (5) Subsection (4) does not apply to a map required by paragraph 8 of subsection (1). O. Reg. 255/11, s. 2 (5). (6) Paragraph 1 of subsection (4) does not apply to a process flow diagram, a piping and instrumentation diagram or a schematic diagram. O. Reg. 255/11, s. 2 (6).
Read the APPLICATIONS FOR ENVIRONMENTAL COMPLIANCE APPROVALS on e-Laws ↗

Made under Environmental Protection Act, R.S.O. 1990, c. E.19.