Performance Standards for the Practice of Professional Land Surveying, O. Reg. 216/10
Section 37
Project report
Cite as Performance Standards for the Practice of Professional Land Surveying, O. Reg. 216/10, s. 37 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
When performing geodetic surveying for a project, a member shall ensure that the project report described in section 4, in addition to complying with that section, includes or makes reference to,
(a) the number of new control stations;
(b) the date and results of the most recent instrument calibrations;
(c) the adjustment and analysis procedures that describe,
(i) the minimally constrained adjustment, so that the latitude and longitude of one existing control point and orthometric or ellipsoidal height of one existing control point are held fixed to their published values,
(ii) the fully constrained adjustment, so that all existing horizontal and vertical control in the network are held fixed to their published provincially recognized values,
(iii) the justification for any rejected observations,
(iv) the verification of any existing control used, and
(v) the geoid model used if the project requires orthometric height. O. Reg. 216/10, s. 37; O. Reg. 507/21, s. 11; O. Reg. 310/25, s. 6.
Read the Performance Standards for the Practice of Professional Land Surveying on e-Laws ↗
Made under Surveyors Act, R.S.O. 1990, c. S.29.