Cost Recovery re section 79.1 OF THE ACT, O. Reg. 330/09
Section 1
Definitions and interpretation
Cite as Cost Recovery re section 79.1 OF THE ACT, O. Reg. 330/09, s. 1 · current to November 11, 2026 · consolidated from July 1, 2023 · read from e-Laws on November 16, 2026
The text
(1) In this Regulation,
“consumer” has the same meaning as in the Electricity Act, 1998; (“consommateur”)
“embedded distributor” means a licensed distributor who is not a market participant and to whom a host distributor distributes electricity; (“distributeur intégré”)
“embedded generator” means a generator who is not a market participant and whose generation facility is connected to a distribution system of a licensed distributor, but does not include a generator who consumes more electricity than it generates; (“producteur intégré”)
“host distributor” means a licensed distributor who is a market participant and who distributes electricity to another licensed distributor who is not a market participant; (“distributeur hôte”)
“licensed distributor” means a distributor who is licensed under Part V of the Act; (“distributeur titulaire d’un permis”)
“qualified distributor” means a distributor serving consumers or classes of consumers that are being provided rate protection pursuant to subsection 79.1 (1) of the Act in accordance with this Regulation; (“distributeur admissible”)
“rate protection” means rate protection under section 79.1 of the Act. (“protection des tarifs”) O. Reg. 330/09, s. 1 (1).
(2) The prescribed criterion for falling within the definition of an “eligible investment” under subsection 79.1 (5) of the Act is that the costs associated with the investment are determined to be the responsibility of the distributor in accordance with the Board’s Distribution System Code. O. Reg. 330/09, s. 1 (2).
(3) The prescribed criterion for falling within the definition of a “qualifying generation facility” under subsection 79.1 (5) of the Act is that the generation facility satisfies the criteria necessary to be a renewable energy generation facility under the Electricity Act, 1998. O. Reg. 330/09, s. 1 (3).
Read the Cost Recovery re section 79.1 OF THE ACT on e-Laws ↗
Made under Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B.