TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS, O. Reg. 231/08
Section 14
Statement of completion of project assessment process
Cite as TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS, O. Reg. 231/08, s. 14 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) The proponent may submit a statement of completion of the project assessment process to the Director of the Environmental Assessment Branch if,
(a) the Minister gives the proponent a notice under clause 12 (1) (a) allowing the proponent to proceed with the transit or rail project in accordance with the environmental project report;
(b) the Minister gives the proponent a notice under clause 12 (1) (c) allowing the proponent to proceed with the transit or rail project in accordance with the environmental project report, subject to conditions set out in the notice;
(c) no notice is given by the Minister under subsection 12 (1) within the time period specified in that subsection;
(d) the Minister gives the proponent a notice under clause 13 (4) (a) allowing the proponent to proceed with the transit or rail project in accordance with a revised environmental project report; or
(e) the proponent gives a copy of a revised environmental project report to the Minister under subsection 13 (2) and no notice is given by the Minister under subsection 13 (4) within the time period specified in subsection 13 (4). O. Reg. 231/08, s. 14 (1); O. Reg. 354/12, s. 7; O. Reg. 342/20, s. 11; O. Reg. 52/24, s. 11, 15, 16.
(2) The statement of completion of the project assessment process shall indicate that the proponent intends to proceed with the transit or rail project in accordance with,
(a) the environmental project report, if clause (1) (a) or (c) applies;
(b) the environmental project report, subject to the conditions set out by the Minister in the notice under clause 12 (1) (c), if clause (1) (b) applies; or
(c) the revised environmental project report, if clause (1) (d) or (e) applies. O. Reg. 231/08, s. 14 (2); O. Reg. 52/24, s. 15, 16.
(3) The proponent shall also post the statement of completion of the project assessment process on its website, if any. O. Reg. 231/08, s. 14 (3); O. Reg. 52/24, s. 15.
(4) Subject to subsection 15 (24), if the proponent proceeds with the transit or rail project, the proponent shall proceed in accordance with,
(a) the environmental project report, if clause (1) (a) or (c) applies;
(b) the environmental project report, subject to conditions set out by the Minister in the notice under clause 12 (1) (c), if clause (1) (b) applies; or
(c) the revised environmental project report, if clause (1) (d) or (e) applies. O. Reg. 231/08, s. 14 (4); O. Reg. 52/24, s. 16.
(5) For the purposes of clause (4) (b), if a notice has been given under subsection 12 (1.1), the proponent shall proceed with the transit or rail project in accordance with,
(a) the environmental project report, subject to conditions as amended by the Minister under subsection 12 (1.1); and
(b) any transitional requirements set out by the Minister in the notice under subsection 12 (1.1). O. Reg. 244/23, s. 2; O. Reg. 52/24, s. 16.
Read the TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.