Generation Facilities, O. Reg. 574/06
Schedule 8
Cite as Generation Facilities, O. Reg. 574/06, Schedule 8 · current to November 11, 2026 · consolidated from December 21, 2006 · read from e-Laws on November 16, 2026
The text
Schedule 8 prescribed buildings and structures — bruce B, Bruce generation station (Assessment Roll Number 41-08-260-004-23403)
Item | Building/Structure
1. | Powerhouse (Units 5, 6, 7, 8) & Common Services — Reactor Auxiliary Bay
2. | Powerhouse (Units 5, 6, 7, 8) & Common Services — Turbine Auxiliary Bay
3. | Powerhouse (Units 5, 6, 7, 8) & Common Services — Turbine Hall
4. | Powerhouse (Units 5, 6, 7, 8) & Common Services — Service Area
5. | Vacuum Building
6. | Ancillary Services Building
7. | ECI (Emergency Core Injection) Water Storage Tank & Building
8. | ECI (Emergency Core Injection) Accumulator Building
9. | EFADS (Emergency Filtered Air Discharge System) Building
10. | Cooling Water Pumphouse (Unit 5)
11. | Cooling Water Pumphouse (Unit 6)
12. | Cooling Water Pumphouse (Unit 7)
13. | Cooling Water Pumphouse (Unit 8)
14. | Emergency Water & Power Systems Building
15. | Standby Generator Building (Unit 5)
16. | Standby Generator Building (Unit 6)
17. | Fuel Oil Pumphouse (Unit 5 & 6)
18. | Water Treatment Building
19. | BNPD (Bruce Nuclear Power Development) Site Pumphouse
20. | Main Transformers (Unit 5, 6, 7 & 8)
21. | Demineralized Water Tanks
22. | East Service Area Building
23. | Standby Generator Building (Unit 7)
24. | Standby Generator Building (Unit 8)
25. | Fuel Oil Pumphouse (Unit 7 & 8)
26. | Switchyard Relay Building
27. | Switchyard Compressor Building
28. | Water Treatment Access Tunnel
29. | Pressure Relief Duct
30. | Vacuum Building Service Tunnel
31. | Fuelling Duct Corridor
32. | Ancillary Service Building Service Tunnel
33. | Emergency Core Injection Building Access Tunnel