Payments under Section 78.1 of the Act, O. Reg. 53/05
Section 14
Rules governing determination of payment amounts by Board
Cite as Payments under Section 78.1 of the Act, O. Reg. 53/05, s. 14 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
(1) Subject to subsection (2), the Board may establish the form, methodology, assumptions and calculations used in making an order that determines payment amounts to the DNNP generator for the purpose of section 78.1 of the Act. O. Reg. 315/25, s. 12.
(2) The following rules apply to the making of an order by the Board that determines payment amounts to the DNNP generator for the purpose of section 78.1 of the Act:
1. In making its first order under section 78.1 of the Act determining payment amounts to the DNNP generator, the Board shall take into account any amounts described in subsection 11 (3) or 12 (3), as recorded in the applicable variance account.
2. In determining the DNNP generator’s revenue requirement, the Board shall accept as capital costs of the DNNP generator the following costs:
i. The following costs incurred by Ontario Power Generation Inc. in respect of the Darlington New Nuclear Project, to the extent that the Board is satisfied that the costs were prudently incurred:
A. Costs in respect of any asset transferred from Ontario Power Generation Inc. to the DNNP generator, as reflected in the audited schedule of costs that is approved by Ontario Power Generation Inc.’s board of directors as at the transfer date.
B. Costs in respect of any asset licensed by Ontario Power Generation Inc. to the DNNP generator, as reflected in the audited schedule of costs that is approved by Ontario Power Generation Inc.’s board of directors as at the licensing date.
C. Any other costs for which the DNNP generator has reimbursed Ontario Power Generation Inc., as reflected in the audited schedule of costs that is approved by Ontario Power Generation Inc.’s board of directors as at the reimbursement date.
ii. Costs relating to any leasehold improvements made by the DNNP generator in relation to the DNNP Nuclear Generating Station, including with respect to design, development, construction, commissioning or sustaining, to the extent that the Board is satisfied that the costs were prudently incurred.
3. The Board shall ensure that the DNNP generator recovers the non-capital and capital costs incurred and firm financial commitments made for the Darlington New Nuclear Project, including but not limited to the costs incurred for the matters referred to in sub-subclauses 11 (1) (a) (i) (A) to (C), to the extent that the Board is satisfied that,
i. the costs were prudently incurred and directly attributable to the Darlington New Nuclear Project, and
ii. the financial commitments were prudently made and directly attributable to the Darlington New Nuclear Project.
4. The Board shall ensure that the balance recorded in the variance account established under subsection 11 (1) is recovered on a straight line basis over a period not to exceed three years, to the extent that the Board is satisfied that,
i. the revenues and costs were accurately recorded in the account,
ii. the costs were prudently incurred and directly attributable to the Darlington New Nuclear Project,
iii. the financial commitments were prudently made and directly attributable to the Darlington New Nuclear Project, and
iv. the revenues recorded in the account were earned or foregone and are directly attributable to deviations from the Board-approved production forecast for the DNNP Nuclear Generating Station associated with an earlier or later in-service date of any small modular reactor of the DNNP Nuclear Generating Station.
5. In setting payment amounts for the DNNP Nuclear Generating Station, the Board shall,
i. include in the Board-approved revenue requirement of the DNNP generator for each year the amount calculated by multiplying the forecast cumulative capital costs incurred by the DNNP generator in respect of the Darlington New Nuclear Project, other than capital costs incurred in respect of any small modular reactor that has come into service or been abandoned, by Ontario Power Generation Inc.’s long-term debt rate,
ii. ensure that the balance recorded in the variance account established under subsection 12 (1) is recovered on an annual basis in the year following the year in which the balance was recorded, to the extent that the Board is satisfied that the amounts are accurately recorded in the account, and
iii. accept the terms, conditions and pricing methodologies included in any project management, operations, revenue allocation or lease agreements between the DNNP generator and Ontario Power Generation Inc. in respect of the DNNP Nuclear Generating Station.
6. The Board shall ensure that the DNNP generator recovers the balance recorded in the variance account established under subsection 13 (1) on a straight line basis over a period not to exceed three years, to the extent that the Board is satisfied that the costs associated with the borrowing were prudently incurred.
7. In determining the base payment amount for the nuclear facilities and the DNNP Nuclear Generating Station for any year before the effective date of the first DNNP post-construction payment order, the Board shall determine a blended base payment amount for Ontario Power Generation Inc. and the DNNP generator, calculated using the formula:
(A + B) / (C + D)
where,
“A” is the Board-approved revenue requirement for the nuclear facilities for the year,
“B” is the Board-approved revenue requirement for the DNNP Nuclear Generating Station for the year,
“C” is the Board-approved production forecast for the nuclear facilities for the year, and
“D” is the Board-approved production forecast for the DNNP Nuclear Generating Station for the year.
8. In determining any payment amount rider in respect of the recovery of balances recorded in the deferral and variance accounts established for the nuclear facilities and the DNNP Nuclear Generating Station for any year before the effective date of the first DNNP post-construction payment order, the Board shall determine a blended payment amount rider for Ontario Power Generation Inc. and the DNNP generator, calculated according to the formula:
(E + F) / (C + D)
where,
“E” is the sum of the Board-approved amounts for the year in respect of the recovery of balances recorded in all deferral and variance accounts established by Ontario Power Generation Inc. for the nuclear facilities,
“F” is the sum of the Board-approved amounts for the year in respect of the recovery of balances recorded in all deferral and variance accounts established by the DNNP generator for the DNNP Nuclear Generating Station,
“C” is the Board-approved production forecast for the nuclear facilities for the year, and
“D” is the Board-approved production forecast for the DNNP Nuclear Generating Station for the year.
9. In making a DNNP blended payment order, the Board shall require that payments be paid to Ontario Power Generation Inc., acting on its own behalf and as agent and nominee of the DNNP generator. O. Reg. 315/25, s. 12.
Read the Payments under Section 78.1 of the Act on e-Laws ↗