Adjustments under Section 25.33 of the Act, O. Reg. 429/04
Section 8.1
Effect of transfer of load facility re Class A market participant
Cite as Adjustments under Section 25.33 of the Act, O. Reg. 429/04, s. 8.1 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026
The text
(1) In this section,
“effective date” means,
(a) for the purposes of subsections (2) and (3), the day that is 10 business days after the day the IESO receives the notice referred to in clause (2) (d) and any information required under that clause or clause (2) (e), or
(b) for the purposes of subsections (4) to (6), the day that is 10 business days after the day the IESO receives the notice referred to in clause (4) (f) and any information required under that clause or clause (4) (g). O. Reg. 257/22, s. 13; O. Reg. 101/25, s. 2.
(2) Subsection (3) applies to the transfer of title to all of a load facility if,
(a) the transferor is a Class A market participant or a Class B market participant immediately before the effective date;
(b) the transferred load facility is a load facility or an embedded load facility, as those terms are defined in the market rules;
(c) the transferee is a market participant;
(d) the transferee provides written notice of the transfer, the legal names of the transferor and transferee, and the date of the transfer to the IESO; and
(e) the transferee provides to the IESO such additional information regarding the transferor, the transferee or the transfer as the IESO may request, within the time specified in the request. O. Reg. 257/22, s. 13.
(3) If this subsection applies to the transfer of title to all of a load facility, the following rules apply to the transferee:
1. If the transferor was a Class A market participant in respect of the transferred load facility immediately before the effective date, the transferee is deemed to be a Class A market participant in respect of that load facility for the remainder of the adjustment period on and after the effective date, and to have the same peak demand factor in respect of that load facility as calculated for the transferor immediately before the effective date.
2. For the purposes of determining if the transferee is a Class A market participant, and determining the transferee’s peak demand factor, in respect of the transferred load facility for the next adjustment period following the adjustment period in which the effective date occurs, the following rules apply:
i. The transferee is deemed to have been a market participant for any portion of the applicable base period during which the transferred load facility was registered with the IESO in accordance with the market rules.
ii. The volume of electricity withdrawn from the IESO-controlled grid in respect of the transferred load facility during the applicable base period is deemed to have been withdrawn by the transferee and not the transferor.
iii. Revoked: O. Reg. 101/25, s. 3.
iv. The volume of electricity supplied to the IESO-controlled grid in respect of the transferred load facility during the applicable base period is deemed to have been supplied by the transferee and not the transferor. O. Reg. 257/22, s. 13; O. Reg. 101/25, s. 3.
(4) Subsection (6) applies to the transfer of title to a portion of a load facility if,
(a) the transferor is a Class A market participant in respect of the load facility immediately before the effective date;
(b) the transferred load facility is a load facility or an embedded load facility, as those terms are defined in the market rules;
(c) the transferor is invoiced for electricity withdrawn from the IESO-controlled grid in respect of the transferred and untransferred portions of the facility before the effective date;
(d) the transferred portion of the transferor’s load facility is registered with the IESO by the transferee as of the effective date;
(e) the transferor and the transferee could reasonably be expected to be Class A market participants for each adjustment period listed in clause (i) in respect of their respective portion of the load facility;
(f) the transferee provides written notice of the transfer, the legal names of the transferor and transferee, a copy of the agreement referred to in clause (i) and the date of the transfer to the IESO;
(g) the transferee provides to the IESO such additional information regarding the transferor, the transferee or the transfer as the IESO may request, within the time specified in the request;
(h) if the transferor is an eligible cogeneration customer in respect of the adjustment period in which the effective date occurs, each of the transferor and the transferee is, or may reasonably be expected to be, an eligible cogeneration customer in respect of that adjustment period; and
(i) the transferor and the transferee have reached an agreement described in subsection (5) with respect to the load facility for,
(i) the remainder of the adjustment period in which the effective date occurs,
(ii) the adjustment period commencing immediately after the one referred to in subclause (i), and
(iii) if the effective date occurs between May 1 and June 30, the adjustment period commencing immediately after the one referred to in subclause (ii). O. Reg. 257/22, s. 13.
(5) The agreement referred to in clause (4) (i) must provide for the following:
1. The peak demand factor of the transferor and the transferee for each adjustment period referred to in clause 4 (i), determined as a percentage of the peak demand factor that would be calculated for the transferor in respect of the load facility for that adjustment period if the transfer did not occur. The sum of the peak demand factor of the transferor and the transferee for each such adjustment period must be equal to the peak demand factor that would be calculated for the transferor in respect of the load facility for that adjustment period if the transfer did not occur.
2. Such other information that the IESO may require to determine whether the transferor and the transferee are Class A market participants in respect of each adjustment period referred to in clause (4) (i), and calculate the peak demand factor of the transferor and the transferee in respect of that adjustment period. O. Reg. 257/22, s. 13.
(6) If this subsection applies to the transfer of title to a portion of a load facility, the following rules apply to the transferor and transferee:
1. The transferor and the transferee are deemed to be Class A market participants for each adjustment period referred to in clause (4) (i).
2. The IESO shall calculate or re-calculate the peak demand factor of the transferor and the transferee for each adjustment period referred to in clause (4) (i), based on the agreement referred to in that clause. O. Reg. 257/22, s. 13.
Read the Adjustments under Section 25.33 of the Act on e-Laws ↗
Made under Electricity Act, 1998, S.O. 1998, c. 15, Sched. A.