Adjustments under Section 25.33 of the Act, O. Reg. 429/04
Section 7.1
Class A and B market participants - calculation required for separate load facilities
Cite as Adjustments under Section 25.33 of the Act, O. Reg. 429/04, s. 7.1 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026
The text
(1) For the purpose of paragraph 3 of subsection 7 (1), a market participant’s maximum hourly demand for electricity in a month, as determined by the IESO, shall be determined separately for each of its load facilities. O. Reg. 163/12, s. 1.
(2) For the purpose of subsection 7 (1), a market participant in Ontario,
(a) is a Class A market participant for an adjustment period under this Part in respect of each of its load facilities for which the maximum hourly demand for electricity in a month, as determined by the IESO, exceeds an average of 5 megawatts for the applicable base period; and
(b) is a Class B market participant for an adjustment period under this Part in respect of each of its load facilities for which the maximum hourly demand for electricity in a month, as determined by the IESO, does not exceed an average of 5 megawatts for the applicable base period. O. Reg. 163/12, s. 1.
(3) For the purpose of making any other determination or calculation under this Regulation in respect of a market participant in Ontario that is both a Class A market participant and a Class B market participant, one determination or calculation shall be made for each of the load facilities in respect of which the market participant is a Class A market participant and one determination or calculation shall be made for each of the load facilities in respect of which the market participant is a Class B market participant. O. Reg. 257/22, s. 9.
(4) Subsections (1), (2) and (3) do not apply to a person or entity that was a Class A market participant, as determined in the base period ending April 30, 2012, in respect of each of its load facilities that is described in one of the following paragraphs:
1. The load facility was registered by the market participant with the IESO on or before June 1, 2012.
2. The load facility was the subject of a written notice given by the market participant to the IESO on or before June 1, 2012 of the market participant’s intention to register the load facility with the IESO. O. Reg. 163/12, s. 1.
(5) Revoked: O. Reg. 116/23, s. 3.
Read the Adjustments under Section 25.33 of the Act on e-Laws ↗
Made under Electricity Act, 1998, S.O. 1998, c. 15, Sched. A.