Electrical distribution safety, O. Reg. 22/04
Section 15
Compliance
Cite as Electrical distribution safety, O. Reg. 22/04, s. 15 · current to November 11, 2026 · consolidated from October 1, 2017 · read from e-Laws on November 16, 2026
The text
(1) A distributor that is notified by the Authority that the distributor is not in compliance with any or all provisions of this Regulation shall remedy the non-compliance within the time set out in the notice. O. Reg. 22/04, s. 15 (1).
(2) If a distributor fails to remedy non-compliance with section 6 as required under subsection (1), the distributor shall immediately apply to the Authority for approval of equipment in accordance with Rule 2-024 of the ESC and the distributor may not use any other means available to obtain the approval. O. Reg. 22/04, s. 15 (2).
(3) If a distributor fails to remedy non-compliance with section 7 as required under subsection (1), the distributor shall obtain approval of plans, standard design drawings and standard design specifications by the Authority under clause 7 (2) (b) and subsection 7 (5) and the distributor may not use any other means available to obtain the approval. O. Reg. 22/04, s. 15 (3).
(4) If a distributor fails to remedy non-compliance with section 8 as required under subsection (1), the distributor shall obtain inspection and approval of construction by the Authority under clause 8 (2) (c) and subsection 8 (8) and the distributor may not use any other means available to obtain the approval. O. Reg. 22/04, s. 15 (4).
Read the Electrical distribution safety on e-Laws ↗
Made under Electricity Act, 1998, S.O. 1998, c. 15, Sched. A.