Section 3
Leave to construct hydrocarbon line
Cite as general, O. Reg. 328/03, s. 3 · current to November 11, 2026 · consolidated from July 1, 2025 · read from e-Laws on November 16, 2026
The text
(1) The amount for the projected cost of a proposed hydrocarbon line for the purposes of clause 90 (1) (b) of the Act is $2 million. O. Reg. 328/03, s. 3.
(2) Subsection 90 (1) of the Act applies to the relocation or reconstruction of a hydrocarbon line only if any of the following conditions is met:
1. The diameter of the line is increased.
2. The acquisition of additional land or authority to use additional land is necessary, subject to subsection (3). O. Reg. 274/24, s. 2.
(3) Paragraph 2 of subsection (2) does not apply if the Board makes a determination, on application, that leave under subsection 90 (1) of the Act is not required with respect to the relocation or reconstruction because,
(a) the relocation or reconstruction is being requested by a person other than the applicant, and,
(i) any additional land required for the relocation or reconstruction is under the requesting person’s control, and
(ii) the relocation or reconstruction is undertaken pursuant to an agreement between the applicant and the requesting person that specifies that the cost of the relocation or reconstruction is to be paid for wholly or partly by the requesting person; and
(b) the Board makes a determination that the Crown’s duty to consult, if it applies in respect of the application, has been adequately discharged. O. Reg. 274/24, s. 2; O. Reg. 141/25, s. 2 (1).
(4) For the purposes of making a determination under clause (3) (b), the Board shall provide all Indigenous communities that have or may have aboriginal or treaty rights that may be adversely impacted by the proposed hydrocarbon line with a reasonable opportunity to notify the Board of any concerns that the Crown’s duty to consult has not been adequately discharged. O. Reg. 274/24, s. 2.
(5) The Board may, for the purposes of this section, rely on information from the Ministry, if any, as to whether the Crown’s duty to consult applies in respect of the application and the Indigenous communities that have or may have aboriginal or treaty rights that may be adversely impacted by the proposed hydrocarbon line. O. Reg. 274/24, s. 2; O. Reg. 141/25, s. 2 (2).
(6) For greater certainty, an application may be made under subsection (3) with respect to the relocation or reconstruction of a hydrocarbon line even if, before the day Ontario Regulation 274/24 made under the Act came into force, the relocation or reconstruction was the subject of an application for leave under subsection 90 (1) of the Act that was refused or not finally determined before that day. O. Reg. 274/24, s. 2.
Read the general on e-Laws ↗
Made under Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B.