general, O. Reg. 267/03
Section 98.7
Requirements re biogas
Cite as general, O. Reg. 267/03, s. 98.7 · current to November 11, 2026 · consolidated from April 1, 2024 · read from e-Laws on November 16, 2026
The text
(1) No person shall treat anaerobic digestion materials in a regulated mixed anaerobic digestion facility on a farm unit on which an agricultural operation is carried out unless,
(a) the facility is equipped with, connected to or has access to one or more gas combustion systems or biogas upgrading systems that are collectively capable of consuming the equivalent of 110 per cent of the biogas that the facility can generate;
(b) any gas storage cover installed in respect of the facility has a design permeability of less than 500 cm3/m2/day/bar; and
(c) there is compliance with subsection (3) or (4), as the case may be. O. Reg. 284/13, s. 11; O. Reg. 508/21, s. 23 (1).
(2) The design permeability requirement in clause (1) (b) does not apply if the gas storage cover was installed in respect of the facility before October 25, 2013. O. Reg. 284/13, s. 11.
(3) If the regulated mixed anaerobic digestion facility is designed to generate biogas at a rate that does not exceed 50 m³/hour, a secondary gas burning facility must be available, but need not be located on the farm unit at all times, and must be used within 48 hours if the rate of release of non-combusted biogas exceeds 20 m³/hour. O. Reg. 284/13, s. 11.
(4) If the regulated mixed anaerobic digestion facility is designed to generate biogas at a rate that exceeds 50 m³/hour, a secondary gas burning facility must be available, must be located on the farm unit at all times, and must be used to prevent any release of non-combusted biogas. O. Reg. 284/13, s. 11; O. Reg. 508/21, s. 23 (2).
(5) If the regulated mixed anaerobic digestion facility receives more than 10,000 cubic metres of off-farm anaerobic materials in the preceding 12-month period or if it receives materials listed in Schedule 2B in the preceding 12-month period,
(a) the secondary gas burning facility must be a high efficiency flare that meets the following requirements:
(i) the flare must be designed by a professional engineer, and
(ii) the flare must be sized by the professional engineer to consume 110% of the biogas production capacity of the facility; and
(b) any biogas or renewable natural gas that is not used, consumed or removed from the facility must be disposed of in the flare described in clause (a). O. Reg. 508/21, s. 23 (3).
Read the general on e-Laws ↗
Made under Nutrient Management Act, 2002, S.O. 2002, c. 4.