(1) On and after October 25, 2013, no person shall construct, on a farm unit on which an agricultural operation is carried out, a regulated mixed anaerobic digestion facility that is located,
(a) within 200 metres of a dwelling;
(b) within 450 metres of a residential area; or
(c) within 450 metres of a commercial, community or institutional use. O. Reg. 284/13, s. 8.
(2) For the purposes of subsection (1), the location of the dwelling, residential area or commercial, community or institutional use shall be determined as of the day on which the nutrient management strategy contemplating the construction of the facility is submitted to the Director for approval. O. Reg. 284/13, s. 8.
(3) Clause (1) (a) does not apply between a component of the regulated mixed anaerobic digestion facility and a dwelling that is located on the same property as the component of the regulated mixed anaerobic digestion facility. O. Reg. 508/21, s. 16.
(4) Clause (1) (c) does not apply between a component of the regulated mixed anaerobic digestion facility and a commercial, community or institutional use that is located on the same property as the component of the regulated mixed anaerobic digestion facility. O. Reg. 508/21, s. 16.
(5) Subject to subsections 98.4 (2) to (15), no person shall operate a regulated mixed anaerobic digestion facility constructed on or after July 1, 2021 that does not meet the setbacks described in subsections 98.2.1 (1) and (2). O. Reg. 508/21, s. 16.
(6) In this section,