Water power leases — Niagara Parks Commission, O. Reg. 135/02

Section 5

Prescribed payments for 2003 and after

Cite as Water power leases — Niagara Parks Commission, O. Reg. 135/02, s. 5 · current to November 11, 2026 · consolidated from May 23, 2006 · read from e-Laws on November 16, 2026

The text

The amount of the payment to the Commission required to be made by OPG-Niagara Plant Group Inc. under subsection 92.1 (5.1) of the Act for 2003 and each subsequent year is the amount calculated using the formula, C × D/E in which, “C” is the amount payable by OPG-Niagara Plant Group Inc. under subsection 92.1 (5.1) of the Act for the year immediately preceding the year to which the payment relates, “D” is the CPI for the year to which the payment relates, and “E” is the CPI for the year immediately preceding the year to which the payment relates.
Read the Water power leases — Niagara Parks Commission on e-Laws ↗

Made under Electricity Act, 1998, S.O. 1998, c. 15, Sched. A.