Boilers and Pressure Vessels, O. Reg. 220/01

Section 4

Design registration requirement

Cite as Boilers and Pressure Vessels, O. Reg. 220/01, s. 4 · current to November 11, 2026 · consolidated from July 1, 2018 · read from e-Laws on November 16, 2026

The text

(1) Subject to subsection (2), no person shall manufacture a boiler, pressure vessel, fitting or piping for use in Ontario unless its design is registered with the director. O. Reg. 220/01, s. 4 (1). (2) A person who submits a design submission for registration may commence construction of the boiler, pressure vessel, fitting or piping before the submission is registered if the person assumes all risks related to the construction, whether for an installation or alteration. O. Reg. 220/01, s. 4 (2). (3) The design for a boiler or pressure vessel shall bear the signature and seal of a professional engineer who is experienced in the design of boilers, pressure vessels, piping or fittings. O. Reg. 220/01, s. 4 (3). (4) Where the designer, manufacturer, installer or owner of a boiler, pressure vessel, fitting or piping proposes a change to its registered design, as determined in accordance with the code adoption document, they shall submit the design and specifications of the change to the director and obtain registration before beginning to make the change. O. Reg. 220/01, s. 4 (4). (5) If an inspector finds, after its manufacture or installation, that a boiler, pressure vessel, fitting or piping for which a design registration has been issued is defective, the inspector may, despite the fact that the registration has been issued, permit the boiler, pressure vessel, fitting or piping to be operated or used within such limits of safety as the inspector considers adequate in the circumstances and shall require the manufacturer or installer to correct the defects within such period as the inspector may allow. O. Reg. 220/01, s. 4 (5). (6) If the defects found under subsection (5) are due to the design and specifications of the boiler, pressure vessel, fitting or piping and, in the director’s opinion, they cannot be remedied, the director shall cancel the design registration, and no additional boiler, pressure vessel, fitting or piping shall be manufactured or installed based on that design. O. Reg. 220/01, s. 4 (6). (7) Where a boiler, pressure vessel, piping or fitting has not been manufactured or installed in conformity with its registered design but nevertheless may be used safely at a lower pressure than its design pressure, the inspector shall fix its maximum allowable working pressure having regard to its design, condition and installation and the purpose for which it is to be operated or used. O. Reg. 220/01, s. 4 (7). (8) Where an unused boiler or pressure vessel has been manufactured and its design and specifications have not been registered, the director may cause it to be inspected and, if satisfied that it may be operated or used safely, may issue a certificate of inspection for it as a used boiler or pressure vessel. O. Reg. 220/01, s. 4 (8).
Read the Boilers and Pressure Vessels on e-Laws ↗

Made under Technical Standards and Safety Act, 2000, S.O. 2000, c. 16.