Woods Workers’ Lien Act, c. W-12.5
Section 6
Time limitation respecting statement of lien, effect of transfer during period of lien
Cite as Woods Workers’ Lien Act, c. W-12.5, s. 6 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Where the claim is in respect of
(a) labour or services performed in the woods in connection with any logs or timber, the statement of claim shall be filed within thirty days after the last day on which the labour or service was performed; and
(b) labour or services performed
(i) in stream driving, or otherwise than in the woods, in connection with any logs or timber, or
(ii) in or about a saw mill,
the statement of claim shall be filed within twenty days after the last day on which the labour or service was performed.
(2) No sale or transfer of the logs, timber or lumber upon which a lien is claimed under this Act
(a) during the time limited for the filing of such statement of claim and previous to the filing thereof, or
(b) after the filing of a lien, and during the time limited for the enforcement thereof,
in any way affects the lien, but the lien remains in force against the logs, timber or lumber in whose ever possession they are found.